Handover
What is a snagging list, and what makes one hold up?
The short answer
A snagging list is the record of work that is incomplete, damaged or not to the required standard, drawn up as a job approaches handover. It has no statutory basis, it is a practical document, not a legal one, but it does most of the work in a defects dispute, because it fixes what was wrong, where, and on what date. A snag is minor and does not stop the building being used; a defect is a failure to build to the contract. Both are the contractor’s to put right, but only defects can stop [practical completion](/blog/what-is-practical-completion) being certified.
At a glance
- Legal status
- None, a practical record, not a statutory one
- Drawn up
- As the works approach handover
- Snag
- Minor; does not prevent use
- Defect
- Not built to the contract; may prevent completion
- Who inspects
- Contract administrator, employer, or a snagging surveyor
- New homes
- NHBC standards set the benchmark for tolerances
- Put right during
- The defects liability period
What has to be on each item?
A list that says "kitchen, poor paintwork" is a complaint. It cannot be assigned, cannot be verified, and six weeks later nobody agrees what it referred to. Six fields turn a complaint into something that closes.
- 01Where. Room, level and elevation. "Plot 4, first floor, bedroom 2, north wall", not "upstairs".
- 02What. The observed condition, not the remedy. "Plaster cracked, 300mm, above door architrave" rather than "needs filling".
- 03Why it fails. The standard it does not meet: the specification, the drawing, a tolerance, or workmanship.
- 04Photograph. Taken at the item, showing enough context to locate it again.
- 05When. The date and time it was raised. This is what makes the list evidence rather than assertion.
- 06Who owns it. The trade or subcontractor responsible, so the list can actually be issued to somebody.
A photograph with no time and no place is worth very little in a dispute. The same photograph stamped with when and where it was taken is close to unarguable.
Free toolSnagging list templateNumbered items with a location, a trade and the sign-off that makes retention release due.How does a snag differ from a defect?
People use the words interchangeably and the contract does not. The distinction decides whether a certificate can be issued.
| Snag | Defect | |
|---|---|---|
| What it is | Minor, cosmetic, incomplete finishing | Work not built to the contract |
| Stops the building being used? | No | Often yes |
| Prevents practical completion? | No | Can do |
| Typical example | Paint runs, a door that binds, a missing seal | Wrong insulation, no fire stopping, failed test |
| Put right | During the defects period | Before completion, or urgently after |
NoteA long list of snags does not become a defect by weight of numbers. Fifty cosmetic items still do not stop a building being occupied, but they may say something about supervision, which is a different conversation.
Who inspects, and when?
On a contract with an administrator, they inspect and issue the list. On a domestic job, the client often does it themselves, or pays an independent snagging surveyor, common on new-build homes, where the surveyor measures against NHBC tolerances rather than opinion.
Timing matters more than most people allow for. Inspect too early and you list work that was always going to be finished; too late and handover slips while the list is worked through. The practical answer on most jobs is a pre-handover walk about two weeks out, then a final one at handover to confirm what closed.
On new homes, the buyer usually gets a further opportunity: most warranty providers expect defects reported in the first two years to be dealt with by the builder directly, so a list made at the end of the first year repays doing properly.
What happens to the list after handover?
It becomes the working document of the defects liability period, commonly six or twelve months from practical completion. Items are assigned, put right, re-inspected and signed off. When the list is empty the certificate of making good is issued, and that is what releases the second half of the retention.
So an open list has a direct cash value. Every item still disputed at the end of the period is holding money that would otherwise have been released, and on a £400,000 contract with 5% retention that is £10,000 sitting against a handful of unresolved lines.
The second half of the retention is released when the list closes. An item nobody has re-inspected is not a quality problem, it is a cash-flow one.
Why do lists made on paper cause trouble?
Not because paper is old-fashioned, but because of what a paper list cannot carry. Three problems recur.
- No location that survives. A note on a drawing marked up in a site hut is meaningless to the subcontractor who receives a typed copy a week later.
- No date on the evidence. Photographs taken on a phone and emailed lose the metadata most people assume travels with them. When the argument is whether damage happened before or after another trade was in the room, that date is the whole answer.
- No record of what closed. Items are ticked off in a version somebody holds and not in the version somebody else holds, and by the end of the period there are three lists that disagree.
None of these is solved by better handwriting. They are solved by the item, the photograph, the position and the time being one record from the moment it is raised.
Questions
Frequently asked
Is a snagging list legally required?
No. There is no statute requiring one and no prescribed form. It matters because of what it proves, in a dispute about defects, a dated, located, photographed list is usually the best evidence either side has.
Can a client refuse to complete because of snags?
Minor snags do not prevent practical completion, so refusing on that basis is generally not open to a client. Items that stop the building being used for its intended purpose are a different matter.
How long does a contractor have to fix snags?
For the length of the defects liability period, usually six or twelve months from practical completion, unless the contract says otherwise. Items raised in that window must be put right before the certificate of making good is issued.
Who pays for a snagging survey?
On a domestic new build the buyer usually pays for an independent survey. On a contract with an administrator, inspection is part of their appointment and the cost sits with the employer.
How does snagging differ from a defects liability period?
Snagging is the act of finding and listing the items. The defects liability period is the contractual window during which the contractor must return and put them right. The list is the document; the period is the time.
Read next
What is retention, and how do you get it released?
Typical percentages, the two release points, and the notices that actually work.
What must a RAMS actually contain?
The legal duty behind it, the sections a good one has, and what gets them rejected.
Estimark: payment applications & retention
Construction Act dates, pay less deadlines and retention release on one screen.
Estimark: reactive maintenance
Priority SLAs measured from report time, with Awaab’s Law presets.
Snagging list template
Numbered items with a location, a trade and the sign-off that makes retention release due.
Retention calculator
What is held, what the cap does to it, and the two dates the money comes back.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee.