Sector — builders & contractors

Construction software for builders and contractors

Estimark Pro costs £249 a month, covers up to fifteen users and unlimited open jobs, and is built for the contractor who has to reconcile cost against value, apply for payment under the Construction Act, deduct CIS correctly and prove who was on site.

What actually goes wrong

01

Cost lands too late

The overrun shows up on the final account, not in month three when you could still have done something about it.

02

You get certified less than you applied for

Without the statutory dates on a calendar, a late pay less notice gets argued about instead of rejected.

03

CIS lives in a spreadsheet

Deducting on the wrong base, or against the wrong tax month, is exactly the kind of mistake HMRC charges for.

04

Nobody can prove who was on site

After an incident, “he was here somewhere” is not an answer you can give an inspector.

Sector — how it works

Can I see where a job is against budget right now?

Yes. Estimark computes a live cost position for every job from three feeds: the cost ledger, timesheets, and purchase orders as they are received.

  • Cost is split across six categories — labour, materials, plant, subcontractor, preliminaries and other.
  • Labour actuals come from timesheet hours multiplied by the rate held on those hours.
  • Materials come in as purchase orders are receipted, pro-rated by the quantity actually received.
  • Committed cost is the VAT-exclusive value of issued orders not yet received, so it is never double counted against the receipted figure.
  • Budget is your active budget baseline if you have set one, or the job’s estimate line items if you have not — and the position tells you which of the two it used.

NoteTimesheets and purchase-order receipts feed cost automatically. Everything else is a cost ledger entry you post yourself.

Does it produce a real CVR?

Yes — a genuine cost value reconciliation, per job and as a whole-portfolio pack, exportable to CSV.

  • Every row carries contract value, approved variations, revised contract value, value certified, actual cost, committed cost, cost to complete and forecast final cost.
  • Margin to date is value certified minus actual cost. Forecast margin is revised contract value minus forecast final cost.
  • Revised contract value includes approved variations, so the CVR is never silently run against the original order value.
  • A separate WIP report shows certified value against invoiced value, with retention held.

Does it handle Construction Act payment dates?

Yes. Estimark computes the statutory dates from the application date and refuses a pay less notice served too late.

  • Due date defaults to 30 days after the application date.
  • The payment notice deadline is 5 days after the due date, under section 110A.
  • The final date for payment defaults to 14 days after the due date.
  • A pay less notice must be served at least 5 days before the final date for payment. Serve it later and Estimark rejects it, quoting the deadline and stating that the notified sum remains payable in full.
  • Retention defaults to 5%, is taken off the gross cumulative valuation, and a release at practical completion or defects-period end raises its own invoice.

NoteThese are the standard JCT-style defaults. They are not yet configurable per contract.

How does CIS work for a contractor?

Estimark deducts on labour only — excluding materials, VAT and plant hire — uses the 6th-to-5th tax month, and records the CIS300 with both statutory declarations. It does not file to HMRC for you.

  • Rates are 0% for gross payment status, 20% for a verified and registered subcontractor and 30% for unverified or unmatched.
  • Verification is a real call to HMRC when you have supplied HMRC credentials. With no connection it refuses rather than inventing a verification number.
  • The monthly return is due by the 19th of the month the tax period ends in, and Estimark flags it overdue past that date.

Can I stop someone clocking on without an induction?

Yes. Site clock-on can be gated on three checks — site induction, an in-date CSCS card and acceptance of the current RAMS version — each set independently to off, warn or block for that job.

  • A blocked clock-on is refused outright and names the check that failed. Warn lets the operative on and records the warning.
  • All three gates ship off by default; you switch them on per job.
  • The QR scan is geofenced, 100 metres by default and configurable from 10 to 5,000 metres.
  • A live muster roll lists everyone currently clocked in — the list a fire marshal reads at the assembly point.

Pro, in numbers

Plan
Pro
Price
£249 / month
Users
Up to 15
Open jobs
Unlimited
Retention default
5%
Pay less deadline
Final date − 5 days
CIS rates
0% / 20% / 30%
Geofence default
100 m
Which plan

Pro

£249/month

Up to fifteen users and unlimited open jobs. Pro includes the Pro-tier modules rather than charging for them one by one.

What you get

  • Job Costing and the CVR pack
  • Payment Applications and retention
  • CIS Compliance and Health & Safety
  • Variations, Purchase Orders, Defects, RFIs
  • Subcontractor and Supplier Management
  • HR, Training, Fleet, Plant & Equipment

Bolt-ons are charged on top of any plan: Reactive Maintenance £299/month, Schedule of Rates £199/month, Property Compliance £149/month, Custom Forms £49/month. Enterprise starts at £999/month with unlimited users.

Every module and price →

Questions

Builders & contractorsfrequently asked

How much is Estimark for a building contractor?

Estimark Pro is £249 a month for up to fifteen users with unlimited open jobs, and includes job costing, payment applications, CIS, health and safety, variations and purchase orders. Core is £99 a month for up to three users and Enterprise starts at £999 a month with unlimited users.

Does Estimark produce a cost value reconciliation?

Yes. Estimark produces a CVR per job and as a whole-portfolio pack, with contract value, approved variations, revised contract value, value certified, actual cost, committed cost, cost to complete, forecast final cost and margin. The pack exports to CSV.

Does Estimark enforce the Construction Act pay less deadline?

Yes. A pay less notice must be served at least five days before the final date for payment. If you try to serve one after that, Estimark rejects it and states that the notified sum remains payable in full. The due date defaults to 30 days after the application, and the final date for payment to 14 days after the due date.

How is committed cost calculated?

Committed cost is the VAT-exclusive value of purchase orders that have been issued but not yet received. Once goods are receipted, that portion moves from committed cost into actual cost, so the same money is never counted twice.