Regulatory change
CDM, the F10 and the Building Safety Act: where the rules stand in 2026
The short answer
In 2026 a project is notifiable to HSE on an F10 exactly as it was in 2015: where the construction work is likely to last longer than 30 working days and have more than 20 workers working simultaneously, or to exceed 500 person days. What has changed since is the Building Safety Act 2022. Since 1 October 2023 every building project in England has had dutyholders under Part 2A of the Building Regulations 2010, with a principal designer and a principal contractor appointed by the client in writing wherever more than one contractor is on the job, separately from the CDM appointments that carry the same names. And a building in England at least 18 metres high or with at least 7 storeys and containing at least 2 residential units is a higher-risk building, whose design and construction go through the Building Safety Regulator rather than a local authority. Northern Ireland has its own CDM regulations of 2016 with the same thresholds, and Wales has its own building safety Act.
At a glance
- F10 threshold A
- >30 working days and >20 workers at once, unchanged
- F10 threshold B
- >500 person days, unchanged
- Building Regulations dutyholders
- Every project in England since 1 October 2023
- Higher-risk building
- 18 metres or 7 storeys, and 2 residential units
- Higher-risk building control
- The Building Safety Regulator, since 1 October 2023
- Northern Ireland CDM
- S.R. 2016/146, since 1 August 2016
- Wales
- Building Safety (Wales) Act 2026, three categories
- Estimark
- Records the CDM appointments and the F10; prepares no regulator application
Has the F10 threshold changed?
No. Regulation 6 of the Construction (Design and Management) Regulations 2015 is as it was made. A project is notifiable if the construction work is likely to last longer than 30 working days and have more than 20 workers working simultaneously at any point, or is likely to exceed 500 person days. The client notifies, as soon as is practicable before the construction phase begins, and a construction phase plan is required on every project whether or not it is notified.
The rumour that it changed usually comes from two places. One is memory of CDM 2007, under which duration alone triggered notification at 30 days, and which the 2015 regulations replaced with the two-condition first limb. The other is the Building Safety Act, which added a second set of dutyholders with the same names as CDM’s and is read as a change to CDM. It is not. CDM 2015 is a health and safety regulation made under the Health and Safety at Work Act; the new dutyholders are in the Building Regulations, made under the Building Act.
Northern Ireland runs the same thresholds under its own instrument. The Construction (Design and Management) Regulations (Northern Ireland) 2016 have been in operation since 1 August 2016, and regulation 6 notifies the Health and Safety Executive for Northern Ireland on the same two limbs.
The first F10 limb needs both conditions. Thirty-five working days with six operatives on site is not notifiable on it.
What did the Building Safety Act add for every project in England?
Part 2A of the Building Regulations 2010, inserted by the Building Regulations etc. (Amendment) (England) Regulations 2023 and in force since 1 October 2023. It gives every building project in England a client, designers and contractors with duties under the Building Regulations, and where more than one contractor is or will be working on the project, a principal designer and a principal contractor appointed by the client in writing before the construction phase begins. It also sets competence requirements for each of them.
The names are CDM 2015’s and the appointments are not. A firm appointed principal contractor under CDM has not, by that act, been appointed principal contractor under the Building Regulations. The client has to make both appointments, and can make them to different people. On a domestic extension with a builder and an electrician the builder is very likely to be both, and still has to be appointed as both, in writing.
- CDM 2015 asks whether the work is safe to build. Part 2A asks whether it complies with the Building Regulations. The same person can hold both duties and the duties are different.
- Both regimes turn on the same trigger: more than one contractor on the project.
- Both appointments have to be in writing, and neither is made by the other.
NoteThe trap is a contract that appoints “the Principal Contractor” once, in capitals, and means CDM. A subcontract written before October 2023 and reused since may still do exactly that.
What is a higher-risk building, and what is different about it?
Section 65 of the Building Safety Act 2022 defines a higher-risk building as one in England that is at least 18 metres in height or has at least 7 storeys, and contains at least 2 residential units. For the design and construction phase the description also takes in care homes and hospitals that meet the height or storey condition.
Since 1 October 2023 the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 have routed the design and construction of those buildings through the Building Safety Regulator rather than a local authority or an approved inspector. The regulator’s building control approval is needed before the work starts, and its completion certificate before the building is occupied. Those are the two stages the industry calls gateways two and three.
| Building | Building control body in England | Route |
|---|---|---|
| A house, an extension, a loft conversion, a change of use, a new build below the threshold | Local authority building control, or a private approver | Full plans, building notice, or regularisation |
| At least 18 metres or 7 storeys, with at least 2 residential units | The Building Safety Regulator | Building control approval before work; completion certificate before occupation |
| A care home or hospital meeting the height condition | The Building Safety Regulator, for design and construction | As above |
The regime applies in England. Wales has legislated separately: the Building Safety (Wales) Act 2026 sets three categories of multi-occupied residential building, Category 1 at least 18 metres or 7 storeys, Category 2 at least 11 metres or 5 storeys but below Category 1, and Category 3 below that, for the occupation phase. Scotland routes all building work through a building warrant from the verifier and a completion certificate under the Building (Scotland) Act 2003, and Northern Ireland through the Building Regulations (Northern Ireland) 2012.
Free toolRAMS templateThe document a principal contractor under either regime asks a subcontractor for first.What should a contractor do on a project starting this year?
- 01Count the person days as well as the workers. A long job with a small crew is where the 500-person-day limb catches people, and it is the limb nobody checks.
- 02On any project in England with more than one contractor, get both principal appointments in writing: CDM 2015 and Building Regulations Part 2A. One letter naming both regimes is enough. One letter naming one is not.
- 03Write a construction phase plan for every job, notifiable or not. One or two pages for a small job, specific to the site.
- 04If the building is at or near 18 metres or 7 storeys and has two or more homes in it, stop and check whether it is higher-risk before anything is submitted anywhere, because the building control body is a different one.
- 05Keep the health and safety file for the client at the end. Under the higher-risk regime the golden thread of building information is a separate obligation from it.
What does Estimark record?
A CDM project record against the job: whether the project is notifiable, the principal designer and principal contractor by name and company, the estimated duration and the maximum number of workers on site, the pre-construction information, the construction phase plan and the health and safety file. Beside it, an F10 record holds the particulars a notification needs, the client, the site address, the principals, the construction phase start, the expected duration and the maximum workers, and whether it has been submitted.
The Health & Safety module around it holds versioned RAMS signed per operative, site inductions, toolbox talks with a signed attendance list, permits to work and near-miss reporting, and can gate QR site clock-on on induction, CSCS card and a signed current RAMS. It is included from Solo.
NoteWhat it does not do. Estimark does not submit the F10 to HSE; you submit it on HSE’s own service and record that you did. It prepares nothing for the Building Safety Regulator and holds no golden thread. And it has no separate record for a Building Regulations Part 2A appointment: it holds the CDM one, and where both apply the second is a document you keep. See RAMS and site safety in Estimark.
Questions
Frequently asked
Has the CDM notification threshold changed in 2026?
No. A project is notifiable where the construction work is likely to last longer than 30 working days and have more than 20 workers working simultaneously, or to exceed 500 person days, under regulation 6 of CDM 2015. Northern Ireland’s 2016 regulations use the same thresholds.
Is a Building Regulations principal contractor the same as a CDM principal contractor?
No. Since 1 October 2023 the Building Regulations in England have had their own principal designer and principal contractor under Part 2A, appointed by the client in writing where more than one contractor is on the project. The names match CDM 2015 and the appointments are separate. The same firm can hold both, and has to be appointed to both.
What is a higher-risk building?
Under section 65 of the Building Safety Act 2022, a building in England at least 18 metres high or with at least 7 storeys that contains at least 2 residential units. For design and construction the description also covers care homes and hospitals meeting the height condition. Its building control body is the Building Safety Regulator.
Does the Building Safety Act apply in Wales, Scotland or Northern Ireland?
The higher-risk building procedures and the Part 2A dutyholders commenced in 2023 apply in England. Wales has the Building Safety (Wales) Act 2026 with its own three categories from 11 metres. Scotland uses building warrants and completion certificates under the Building (Scotland) Act 2003. Northern Ireland has the Building Regulations (Northern Ireland) 2012 and its own CDM regulations of 2016.
Does Estimark submit the F10 or apply to the Building Safety Regulator?
Neither. It holds the CDM project record and the F10 particulars and records that a notification was submitted. The F10 goes in on HSE’s own service, and a higher-risk building application is prepared outside Estimark.
Read next
CDM 2015: when do I notify HSE on an F10?
The two thresholds, who notifies, and the duties that apply whether you notify or not.
What must a RAMS actually contain?
The legal duty behind it, the sections a good one has, and what gets them rejected.
Awaab’s Law Phase 2: what changes on 30 November 2026
Nine hazard categories join the clocks, a definition moves, and Scotland starts its own on 6 October.
Estimark: RAMS & site safety
Versioned RAMS, operative sign-off, inductions and a live muster roll.
RAMS template
Risk assessment, method statement, emergency arrangements and a signed briefing record.
UK construction compliance calendar