Health & Safety

Construction phase plan: who writes it, and when is it required?

5 min read

The short answer

A construction phase plan is the document setting out the health and safety arrangements, site rules and specific measures for the construction work on a project. Regulation 12 of the Construction (Design and Management) Regulations 2015 requires one for **every** construction project, there is no exemption for small or domestic work, and no notification threshold to cross first. On a project with more than one contractor the principal contractor prepares it; on a single-contractor project the contractor does. It must exist before the construction phase begins, and it must be specific to that site: a downloaded template with the address changed is the failing most often written up.

At a glance

Regulation
CDM 2015, regulation 12
Required on
Every construction project, without exception
Domestic projects
Also required
Who writes it. 1 contractor
The contractor
Who writes it. 2+ contractors
The principal contractor
When
Before the construction phase begins
Not the same as
The health and safety file, or an F10
Review
Updated as the work and the risks change

Is it really required on every project?

Yes, and this is the most common misunderstanding about CDM 2015. Three separate thresholds get confused with each other, and only one of them has anything to do with the plan.

RequirementThresholdApplies to a two-week domestic job?
Construction phase planNone, every projectYes
F10 notification to HSE>30 working days with 20+ workers at once, or >500 person daysUsually no
Principal designer & contractorMore than one contractorOften yes
Health and safety fileMore than one contractorOften yes

Notification and the plan are different tests. A job can be far too small to notify and still require a construction phase plan, because every job does.

For domestic clients the duties do not disappear, they transfer: the client’s duties pass to the contractor, or to the principal contractor where there is more than one. See when CDM applies and what the F10 is for.

Free toolRAMS templateThe RAMS that feeds the plan, with risk scored before and after the controls.

What must it contain?

CDM 2015 does not prescribe a format. It requires the plan to set out the arrangements for the project and the site rules, taking account of the risks involved. In practice an inspector expects to find five things.

  1. 01Project description. What is being built, where, the programme, and who holds each duty holder role with contact details.
  2. 02Management arrangements. Who is responsible for what; how the work is supervised; how workers are inducted, consulted and briefed; how contractors are appointed and checked.
  3. 03Site rules. The things that apply to everybody on site: PPE, permits, access, deliveries, restricted areas, speed limits.
  4. 04Arrangements for controlling significant risks. The specific ones for this site, not a list of every hazard in construction. Work at height, excavations, services, lifting, asbestos, confined spaces, whichever actually apply here.
  5. 05Emergency arrangements. Fire, first aid, evacuation, assembly point, nearest hospital, and who raises the alarm.

NoteThe plan is not a risk assessment and does not replace one. Risk assessments and method statements sit underneath it and are referenced by it. See what a RAMS must contain.

Why do generic templates fail?

Because the regulation asks for arrangements "taking account of the risks involved" on that project, and a template accounts for the risks of no project at all. The tell is usually visible in seconds.

  • Risks that are not on the site. A confined-space section on a loft conversion says nobody read it.
  • Risks that are on the site and not in the plan. The scaffold, the live services, the asbestos survey nobody has actioned.
  • Names and numbers that are wrong. A first aider who left, a principal designer who was never appointed.
  • No dates or revisions. A plan written once and never touched, on a job whose risks changed twice.
  • Nothing about how workers are briefed. The plan can be perfect and worth nothing if the people on site have not seen it.

The proportionality point cuts both ways. A small job does not need a fifty-page document, a short, specific plan is better than a long generic one. But it does need to exist, and it does need to be about this site.

How does it relate to the health and safety file?

They are different documents at different ends of the job, and mixing them up is common.

Construction phase planHealth and safety file
WhenBefore work startsHanded over at the end
AboutHow the work will be done safelyResidual risks for whoever maintains the building
Prepared byPrincipal contractor or contractorPrincipal designer
Required onEvery projectProjects with more than one contractor
AudienceEverybody working on siteThe building’s future owners and maintainers

The plan is live for the duration of the works and should be revised when the work changes. The file is assembled during the project and handed over at practical completion.

What happens if there isn’t one?

Regulation 12 is a legal duty, and the absence of a plan is one of the first things an HSE inspector asks for on an unannounced visit. It is also frequently the finding that follows an accident, because the investigation asks what the arrangements were and the answer has to be a document that predates the incident.

The commercial consequence usually arrives sooner than the regulatory one. Principal contractors ask for the plan at pre-qualification; so do most insurers, and so does anyone operating a PAS 91 or common assessment standard process. A contractor who cannot produce one for the last three jobs will struggle to be appointed on the next.

It has to exist before the construction phase begins. A plan written after an incident, or after an inspector asks, is not evidence of arrangements, it is evidence there were none.

Questions

Frequently asked

Do I need a construction phase plan for a domestic extension?

Yes. CDM 2015 regulation 12 applies to every construction project with no exemption for domestic work or for small jobs. What changes on a domestic project is who holds the client duties, they transfer to the contractor or principal contractor.

Who writes the construction phase plan?

The principal contractor where there is more than one contractor on the project. Where there is only one contractor, that contractor writes it. It is never the client’s job, and it is not the principal designer’s.

Is a construction phase plan the same as a RAMS?

No. The plan covers the whole site, arrangements, site rules and how significant risks are managed. RAMS cover a specific task or activity. The plan sits above them and refers to them.

How long does a construction phase plan need to be?

As long as the risks require and no longer. A short, specific plan for a small job is better than a long generic one. HSE guidance is explicit that the effort should be proportionate to the risk.

Does the plan need to be updated during the job?

Yes. It must be reviewed and revised as the work progresses and the risks change. A plan that is identical on the last day to the first, on a job whose risks changed, has not been managed.

Build on a solid foundation.

Run the whole business without an implementation project and without legacy baggage. Every plan starts with 14 days free.

Estimating · Jobs · Invoicing · CIS · H&S · Reactive maintenance