What is practical completion, and who decides it?
The short answer
Practical completion is the point at which the works are complete for all practical purposes and the employer can take possession and use them for their intended purpose. There is no statutory definition and no fixed percentage: it is a matter of judgement for whoever the contract names, usually the contract administrator, architect or employer’s agent. Certifying it is not a formality, it releases half the retention, stops liquidated damages running, starts the rectification or defects liability period, and passes the risk of insuring the works from contractor to employer. Minor snags do not prevent it, but works that stop the building being used for its purpose do.
At a glance
- Statutory definition
- None, a matter of contract and judgement
- Who certifies
- Contract administrator, architect or employer’s agent
- Retention
- Typically half released on certification
- Liquidated damages
- Stop running
- Defects period
- Starts, commonly 6 or 12 months
- Insurance
- Risk in the works passes to the employer
- JCT term
- Practical completion
- NEC term
- Completion, defined in the contract
What actually changes when it is certified?
Practical completion is worth arguing about because six separate things turn on one date. It is not a ceremony at the end of a job; it is the switch that moves risk and money.
- 01Half the retention is released. The rest is held until the end of the defects period. See retention in construction contracts for how the two halves work.
- 02Liquidated damages stop. If the job is late, the employer’s deduction stops accruing on this date, which is often the largest single sum in dispute.
- 03The defects liability period starts. Commonly six or twelve months. Everything found in that window is the contractor’s to put right.
- 04Insurance passes. The employer becomes responsible for insuring the works. A gap here is how a fire between handover and policy start becomes nobody’s claim.
- 05Possession passes. The employer can occupy and use the building.
- 06The final account clock starts. Most contracts run the period for the final certificate from this date.
A date that moves retention, damages, insurance and the defects clock in one step is worth putting in writing on the day, not reconstructing from memory three months later.
Free toolRetention calculatorPractical completion releases the first half. This works out how much, and when the balance falls due.How complete is “practically complete”?
There is no percentage. The courts have consistently declined to give one, and contracts that try tend to make things worse rather than clearer. The working test that survives is whether the employer can take the building and use it for what it was built for.
Minor snags do not prevent practical completion. That is settled and it is the point of the word "practical". A door that binds, a patch of paint, a missing escutcheon, these are for the defects period, not reasons to withhold a certificate.
Works that stop the building being used do prevent it. No fire alarm commissioning, no working lift in a building that needs one, no certificate for the electrical installation. The distinction is function, not quantity: fifty cosmetic snags may not prevent it while one missing EICR does.
NoteWithholding a certificate to gain leverage on something else, a disputed variation, an unresolved account, is a common tactic and a poor one. If the works are practically complete, the certificate is due, and refusing it has been found to be a breach.
What should be handed over on the day?
Most disputes about practical completion are really disputes about paperwork. The building is finished; the record of it is not. Contracts usually make the handover documents a condition, and a certificate issued without them is an argument waiting to happen.
- Health and safety file. required by CDM 2015 where there is more than one contractor. See the F10 and when CDM applies.
- Test and commissioning certificates. electrical, gas, water, fire alarm, emergency lighting, ventilation.
- As-built drawings and O&M manuals. what was actually built, not what was drawn.
- Warranties and guarantees. roofing, windows, flooring, plant, and anything with a manufacturer-backed term.
- Building control completion certificate. or the approved inspector’s final certificate.
- The agreed snagging list. signed by both sides, with dates against each item.
The last one is the one that most often goes wrong. A snagging list written on the day, agreed by both parties and dated, is what lets a defects period close. Without one it runs for years on disputed items.
How does it differ between JCT and NEC?
| JCT | NEC4 | |
|---|---|---|
| Term used | Practical completion | Completion |
| Defined? | No, left to judgement | Yes, against the Works Information |
| Who decides | Contract administrator / architect | Project manager |
| Deadline to certify | Not fixed | One week from the date of Completion |
| Defects period | Rectification period | Defect correction period |
The practical difference is that NEC tries to remove the judgement and JCT does not.
NEC defines Completion by reference to what the Works Information says must be done, which makes the test documentary rather than a matter of opinion. That is an improvement where the Works Information is good and a problem where it is vague, because then there is nothing to measure against at all.
What about sectional and partial possession?
Two different things, and mixing them up is expensive.
Sectional completion is planned. The contract divides the works into sections, each with its own completion date, its own damages and its own retention. It is in the contract from the start.
Partial possession is not planned. The employer asks to take part of the works early, and the contractor consents. That part is then treated as practically complete: damages stop on it, retention is released proportionally, and insurance passes for that part. Consent is required, an employer cannot simply move in.
NotePartial possession granted informally, with no written record of what was taken or when, is one of the more reliable ways to lose an argument about liquidated damages later.
Questions
Frequently asked
Can practical completion be certified with snags outstanding?
Yes. Minor snags do not prevent practical completion, that is what "practical" means. They go on the snagging list and are put right during the defects liability period. Works that prevent the building being used for its intended purpose are a different matter and do prevent it.
What percentage complete is practical completion?
There is no percentage. No statute or standard form sets one, and the courts have declined to. The test is whether the employer can take possession and use the works for their intended purpose.
Who issues the practical completion certificate?
Whoever the contract names, usually the contract administrator, architect or employer’s agent under JCT, or the project manager under NEC. The contractor does not certify its own completion.
What happens if the certificate is refused unreasonably?
Refusing a certificate that is properly due can be a breach of contract, and the contractor can refer it to adjudication. Because certification stops liquidated damages and releases retention, an unjustified refusal has a direct and calculable cost.
Does practical completion end the contractor’s liability?
No. It starts the defects liability period, during which the contractor must return and put right defects. Liability for latent defects continues after that under the limitation periods, six years for a simple contract, twelve for a deed.
Read next
What is retention, and how do you get it released?
Typical percentages, the two release points, and the notices that actually work.
CDM 2015: when do I notify HSE on an F10?
The two thresholds, who notifies, and the duties that apply whether you notify or not.
What is a pay less notice?
Section 111, the deadline, and why a late notice means you pay the notified sum in full.
Estimark: payment applications & retention
Construction Act dates, pay less deadlines and retention release on one screen.
Retention calculator
What is held, what the cap does to it, and the two dates the money comes back.
Snagging list template
Numbered items with a location, a trade and the sign-off that makes retention release due.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee.