Handover

Defects liability period: what it covers and what it does not

4 min read

The short answer

The defects liability period, called the rectification period in JCT, is the window after [practical completion](/blog/what-is-practical-completion) during which the contractor must return and put right defects that appear. It is commonly six or twelve months. It is a right as much as an obligation: the contractor gets to do the work itself rather than pay somebody else’s bill for it. When the period ends and the listed items are closed, the certificate of making good is issued and the remaining retention is released. Liability does not end there. Latent defects remain actionable for six years from breach under a simple contract, or twelve under a deed.

At a glance

Also called
Rectification period (JCT), defect correction period (NEC)
Starts
At practical completion
Typical length
6 or 12 months
Covers
Defects appearing in the period, from the contract works
Does not cover
Fair wear and tear, misuse, employer-supplied items
Ends with
Certificate of making good
Releases
The remaining retention
Liability after
6 years simple contract, 12 years deed

What counts as a defect?

Work that does not comply with the contract: the specification, the drawings, the standard of workmanship required, or the statutory standards that applied. That is a narrower category than "anything the client is unhappy about", and the distinction takes up most of the period.

ItemContractor’s?Why
Cracked plaster from drying shrinkageUsually yesWorkmanship or accepted making-good
Door binding after a wet winterUsually yesWithin tolerances the contract set
Boiler failure at month nineDependsManufacturer warranty may answer first
Scuffed paint from the client moving inNoNot a defect; damage after handover
Blocked gutter, never clearedNoMaintenance, not a defect
Employer-supplied worktop that failsNoNot the contractor’s material

NoteMost arguments in the period are about the last three rows. A dated snagging list taken at handover is what separates a defect from damage caused after it.

Free toolRetention calculatorThe end of the period releases the balance. Enter the completion date and it gives you both dates.

Why is it a right and not only an obligation?

Because the alternative costs the contractor far more. Without the clause, an employer finding a defect could engage anybody to fix it and claim the cost as damages, at prices the contractor never agreed and with no chance to inspect.

The period gives the contractor the first opportunity to put the work right using its own people and its own subcontractors, at its own cost base. An employer who bypasses that and brings somebody else in generally cannot recover the full cost, because they denied the contractor the chance to mitigate.

An employer who calls somebody else in without asking the contractor first usually recovers less, not more.

How does the money work?

The remaining retention, typically half of the original percentage, is held through the period. When the certificate of making good is issued it is released. See retention in construction contracts for how the two releases are structured.

This makes an open defects list a cash-flow problem rather than a quality one. On a £500,000 contract with 5% retention, £12,500 sits against whatever remains on the list, and it stays there while three disputed items go unresolved for months.

The practical consequence is that closing items quickly is worth more than arguing about whether they were defects. An item worth £200 of labour holds thousands of pounds of retention while it is open.

What happens when the period ends?

  1. 01The contract administrator inspects. Against the list, and against anything else that has appeared.
  2. 02Outstanding items are notified. Usually as a schedule, with a date to complete.
  3. 03The contractor completes them. Or the employer has them done and deducts the reasonable cost.
  4. 04The certificate of making good is issued. This is the trigger, and it is a certificate rather than a date.
  5. 05Final retention is released. And the final account can be concluded.

The certificate does not end liability. It ends the obligation to return under this clause. A defect that was hidden and appears in year four is a matter for the limitation period, not the rectification period.

Questions

Frequently asked

How long is the defects liability period?

Whatever the contract states, commonly six or twelve months from practical completion. Twelve is usual on buildings with heating and cooling, so the installation is seen through a full cycle of seasons.

Does the period restart when a defect is fixed?

Not usually for the whole works. Some contracts restart it for the repaired element only. Check the clause, because a rectification that restarts the period on everything would delay the entire retention release.

Who pays to fix a defect during the period?

The contractor, where it is a genuine defect in the contract works. The employer pays where the item turns out to be damage, misuse, wear or maintenance.

Is the contractor liable after the period ends?

Yes, for latent defects. Six years from the breach under a simple contract and twelve under a deed. The rectification period is a right to return, not a limit on liability.

Can retention be released before the certificate of making good?

Only if the contract allows it or the parties agree. Retention held past the point the contract says it should be released is a debt, and there is a growing appetite to challenge it.

Build on a solid foundation.

Run the whole business without an implementation project and without legacy baggage. Every plan starts with 14 days free.

Estimating · Jobs · Invoicing · CIS · H&S · Reactive maintenance