Estimating
What are preliminaries, and how do you price them?
The short answer
Preliminaries (prelims) are the costs of running a project that cannot be attributed to any single item of measured work: site management, welfare, scaffolding, plant, temporary works, insurance, security and the rest. They typically run between 8% and 15% of contract value, higher on short or constrained jobs. Most of them are time-related rather than quantity-related, which is the single most important thing about them: if the programme extends, the prelims keep running whether or not another brick is laid. Pricing them as a flat percentage is how a four-week delay quietly becomes a loss.
At a glance
- Typical range
- 8–15% of contract value
- Main driver
- Time, not quantity
- Fixed cost
- Incurred once, set up, take down
- Time-related cost
- Runs weekly for the duration
- Standard reference
- NRM2 Section 2 / SMM7 Section A
- Recovered through
- Interim valuations, usually pro rata to time
- Commonest error
- Pricing as a flat percentage of the works
What actually belongs in prelims?
The test is whether the cost can be attributed to a measured item. Bricklaying labour belongs to the brickwork. The site manager who supervises the bricklayer, the welfare unit they use and the scaffold they stand on belong to prelims.
- Management and staff. site manager, agent, engineer, quantity surveyor, first aider. Usually the largest single line.
- Site accommodation and welfare. cabins, drying room, toilets, canteen, and the CDM welfare requirements that are not optional.
- Temporary works. scaffolding, propping, hoardings, temporary roads, edge protection.
- Plant and equipment. crane, hoist, telehandler, generators, small plant not priced in the rates.
- Utilities. temporary power, water, lighting, and the standing charges nobody remembers.
- Security. fencing, gates, cameras, and out-of-hours cover.
- Insurance and bonds. contract works insurance, performance bond, third-party cover.
- Statutory and testing. building control fees, commissioning, testing, and the as-built and O&M documentation required at handover.
- Cleaning and waste. skips, wait-and-load, final clean.
Why does the fixed and time-related split matter so much?
Because it decides who pays for a delay. Split every prelim into the part incurred once and the part incurred every week, and the two behave completely differently when the programme moves.
| Item | Fixed | Time-related |
|---|---|---|
| Deliver and erect scaffold | ✓ | |
| Scaffold hire | ✓ per week | |
| Set up site cabins | ✓ | |
| Cabin hire, power, cleaning | ✓ per week | |
| Site manager | ✓ per week | |
| Contract works insurance | ✓ per week | |
| Final clean | ✓ |
A four-week extension costs you four weeks of every time-related prelim. If they were priced as a percentage of the works, there is no rate to claim them at, and the money comes out of the margin.
This is also what makes a prolongation claim arguable rather than hopeful. If the tender shows the site manager at a weekly rate, an extension of time has an obvious value. If prelims were a single lump labelled "prelims 12%", the claim starts with a fight about what the lump contained.
How do you build the number?
- 01Start from the programme. Prelims are a function of duration. Without a programme you are guessing at the largest time-related costs on the job.
- 02List the resources the programme needs. Who is on site, for how many weeks, and what plant and accommodation they require.
- 03Price each as fixed or weekly. A weekly rate for anything that runs, a one-off for anything that happens once.
- 04Add the statutory and one-off items. Insurance, bonds, building control, testing, commissioning, final clean.
- 05Check the percentage afterwards, as a sense test. If the total lands at 4% or 25% of the works, something is wrong, but the percentage is the check, never the method.
NoteThe percentage is a sense check and nothing more. Working backwards from "prelims are usually 12%" produces a number that cannot be defended in a valuation, cannot be claimed against in an extension, and is wrong on any job that is unusually short, constrained or remote.
How are prelims paid?
Usually through the interim valuations, and usually in proportion to time elapsed rather than work completed, which is the right treatment, because that is how the cost is actually incurred. A job 30% through its programme has spent roughly 30% of its time-related prelims regardless of how much of the measured work is done.
That distinction is worth being explicit about in the payment application. A valuation that recovers prelims against measured progress will under-recover on any job that starts slowly, which is most of them, groundworks and enabling works consume programme without producing much valuable measured work.
Front-loading the fixed items is legitimate and expected: the scaffold really was erected in week one and really was paid for in week one.
What does NRM2 say?
NRM2 (the RICS New Rules of Measurement for detailed measurement) sets out prelims in Section 2, splitting them into employer-provided items and contractor-provided ones, and requiring the fixed and time-related division this article keeps returning to. It replaced SMM7, which many older bills still follow.
Following NRM2 is not compulsory on a private job, but it gives a structure every quantity surveyor recognises, which matters at valuation and matters more at final account. A bill of prelims that follows the standard is easier to agree than one invented for the occasion.
Questions
Frequently asked
What percentage should preliminaries be?
Typically 8–15% of contract value, higher on short, constrained or remote jobs. But the percentage is a sense check after the build-up, not a method for producing the number, prelims are driven by programme duration and the resources it requires.
Are preliminaries the same as overheads?
No. Prelims are site-specific costs of running that project. Overheads are the cost of running the business, office, accounts, directors, marketing, and are recovered separately, usually as a percentage addition across all work.
Can you claim prelims on an extension of time?
Time-related prelims, yes, where the extension carries loss and expense. This is why the fixed and time-related split matters: without weekly rates in the tender there is nothing to calculate the claim from.
Do small jobs need preliminaries?
Every job has them, whether or not they are written down. A domestic extension still needs welfare, waste, insurance and supervision. Not pricing them does not remove the cost, it just moves it into the margin.
Who pays for site welfare?
The contractor, priced in prelims, unless the contract makes it employer-provided. CDM 2015 makes adequate welfare a legal duty from the start of construction work, not something to be provided when convenient.
Read next
How to price a job properly
Labour, materials, plant, preliminaries, overhead recovery and margin, in that order.
What is a Schedule of Rates?
How SOR pricing works, where it beats a quote, and where it’ll lose you money.
Applications for payment vs invoices
Two different documents with two different legal effects. Confusing them costs money.
Estimark: job costing & CVR
Actual, committed and forecast cost per job, reconciled against certified value.
Markup vs margin calculator
Convert between them, and see what price a target margin actually needs.
UK construction glossary
The contractual, tax and safety vocabulary, defined in a sentence each.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee.