Estimating
Provisional sums and PC sums: what each one commits you to
The short answer
A provisional sum is an allowance in the contract for work that cannot be described or measured well enough to price at tender. Under NRM2 it is either defined, where enough information is given for the contractor to have programmed and priced the preliminaries around it, or undefined, where it is not. That difference decides who carries the delay: an undefined sum is deemed not to be in the programme, so expending it can bring an extension of time and loss and expense. A prime cost (PC) sum is different again: an allowance for materials or goods supplied by others, or by a nominated supplier, with the contractor’s profit and attendance added separately.
At a glance
- Provisional sum
- Allowance for work that cannot yet be priced
- Defined
- Enough information to programme and price prelims
- Undefined
- Not deemed to be in the programme
- PC sum
- Allowance for goods or work supplied by others
- Reference
- NRM2, or SMM7 on older bills
- Expended by
- Instruction, then valued as a variation
- Risk on undefined
- Time and money can follow
What has to be stated for a sum to be defined?
NRM2 requires four things. Miss any of them and the sum is undefined, whatever the bill calls it.
- 01The nature and construction of the work. What it is, in enough detail to picture it.
- 02How and where it fits the building. Location and interface with other elements.
- 03A quantity or scope indication. Extent, area, or a range.
- 04Any constraints on sequence or timing. When it must happen relative to everything else.
A bill that says "Provisional sum (defined): drainage alterations, £15,000" and nothing more has not defined anything. The label does not do the work; the four items do.
Why does defined or undefined change the risk?
| Defined | Undefined | |
|---|---|---|
| Allowed for in the programme | Yes, deemed | No |
| Preliminaries priced against it | Yes, deemed | No |
| Extension of time when expended | Not normally | Available |
| Loss and expense | Not normally | Available |
| Who carries the risk | Contractor | Employer |
With a defined sum the contractor is taken to have allowed for the work in its programme and its prelims, so expending it is not a surprise and brings no extra time. With an undefined sum the contractor was not able to plan for it, so the instruction is treated much like a variation and can carry both time and money.
NoteThis is why employers prefer everything defined and contractors read the four requirements carefully at tender. A sum labelled defined but lacking the information is worth querying before the tender goes in, not after the instruction lands.
How is a provisional sum expended?
- 01The sum is removed from the contract. In full. It was never a price for anything.
- 02An instruction is issued. Describing the work now that it can be described.
- 03The work is valued. Using the variation valuation rules: contract rates, adjusted rates, fair rates, then dayworks.
- 04The valuation replaces the sum. The account moves up or down by the difference.
The valuation is not capped by the allowance. A £10,000 provisional sum for work that turns out to cost £18,000 is valued at what the work is worth, and the account increases. The allowance was an estimate for cash-flow purposes, not a limit.
How does a PC sum differ?
A prime cost sum is an allowance for goods or work that somebody else supplies: a nominated subcontractor, a nominated supplier, or an item the employer selects later. Sanitaryware, ironmongery, kitchens and lifts are common examples.
Around the PC sum the contractor prices two further items: profit, as a percentage, and attendance, being the cost of unloading, storing, providing access, scaffolding, power and general facilities to whoever does the work.
When the actual cost is known the PC sum is adjusted, and the profit percentage adjusts with it. Attendance usually does not, because the facilities were provided regardless of what the goods cost.
Pricing attendance at zero to look competitive means providing scaffolding, power and storage to somebody else’s subcontractor for nothing, for the length of their works.
Questions
Frequently asked
Can a provisional sum be omitted entirely?
Yes. If the work is not required, the sum is removed and nothing replaces it. The contractor has no entitlement to the allowance, because it was never a price for work it had won.
What if the actual cost exceeds the provisional sum?
The account increases. The work is valued on its merits under the variation rules, and the allowance is not a cap. Tell the employer early, because the sum is what they budgeted from.
Are provisional sums included in the contract sum?
Yes, they form part of it, then come out and are replaced by the valuation. This matters for percentage-based items such as overheads, insurance and bonds priced against the contract sum.
What is attendance on a PC sum?
The facilities the main contractor provides to the supplier or nominated subcontractor: access, unloading, storage, scaffold, power, welfare, and general attendance. It is priced separately from profit and does not adjust with the goods cost.
Are PC sums still used?
Less than they were. Nomination has largely fallen out of the JCT main forms, and most employers now name subcontractors or use provisional sums instead. PC sums remain common on domestic work for client-chosen fittings.
Read next
What is a Schedule of Rates?
How SOR pricing works, where it beats a quote, and where it’ll lose you money.
How to price a job properly
Labour, materials, plant, preliminaries, overhead recovery and margin, in that order.
Applications for payment vs invoices
Two different documents with two different legal effects. Confusing them costs money.
Estimark: job costing & CVR
Actual, committed and forecast cost per job, reconciled against certified value.
UK construction glossary
The contractual, tax and safety vocabulary, defined in a sentence each.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee.