A retention release request asks the payer, in writing, to pay back retention on the date the contract makes it due: half, commonly, at practical completion and the balance at the end of the rectification period. It names the release event, its date and the contract clause, states the total held and the amount due now, and for the final release lists the defects that were notified and made good. Send it on the day the event happens, because a release nobody asks for is the one that never arrives.
Last reviewed by Estimark. This page states periods and rates set by statute or by standard contract terms. Those move, and this date is when somebody last read the page against its source rather than the day the site was built.
Request for Release of Retention
From and to
Which release this is
Name the event your contract ties the release to, and give its date. A request that names no event invites a reply asking which one.
The sum
Defects
For the second release, list the defects that were notified and when each was made good, with the evidence sent at the time.
| Defect | Notified on | Made good on | Evidence sent |
|---|---|---|---|
Signed
No statute sets a retention rate or the form of a release request. Your contract sets the release events and dates.
In Estimark retention is held against the job on every application, and a release is raised as an invoice that reaches Xero, QuickBooks or Sage like any other.
How do I ask for retention to be released?
In writing, naming the release event your contract sets, its date, the clause, the sum held and the amount due now, and for the final release the defects that were notified and made good.
- Send it the day the event happens rather than waiting to be told. A release nobody asks for is rarely refused, it is forgotten.
- Attach the evidence: the practical completion certificate, the end of the rectification period, and photographs of each defect made good.
- If your contract runs on payment applications, include the release in the next application as well, so it carries the contract’s payment dates.
When is retention due back?
When the contract says. Under most standard forms half is released at practical completion and the balance at the end of the rectification or defects period, commonly six or twelve months later.
- The money is yours throughout. Retention is a deduction from a payment, not a reduction in the contract sum.
- A clause that ties your release to an event under a different contract, such as the main contract’s own certificate of making good, may be ineffective under the Construction Act. Read yours before accepting that answer.
This is a request, not a legal notice. If the payer does not respond, the payment and pay less notice rules of your contract and the Construction Act decide what happens next.
Common questions
- How long can a client hold retention?
- As long as the contract allows and no longer. Under most standard forms the first half is due at practical completion and the balance at the end of the rectification or defects period, commonly six or twelve months later. There is no statutory period.
- What if the client will not release retention?
- Ask in writing, naming the clause and the event, and include it in the next payment application if your contract has them. If it is still refused, adjudication under the Construction Act is available to either party to a construction contract at any time.
- Can retention be held because of outstanding snags?
- For the second release, usually yes: it is commonly conditional on defects being made good. Send the evidence for each item as it is finished so the list is closed before the release date.
Retention calculator
What is held on a valuation and the two dates it comes back.
ReadRetention in construction contracts
Typical percentages, the two release points, and the notices that work.
ReadPayment applications & retention
Construction Act dates, pay less deadlines and retention tracked to release.
ReadSnagging list template
Numbered defects with a location, a trade and a sign-off.
Read