Free template

Variation order template

A variation order records a change to the works instructed under a building contract: who instructed it and when, what changed, how it was priced, and what it does to the contract sum and the completion date, signed by both sides. Most standard forms only recognise a variation instructed in writing by the person the contract names, so the written record is what gets the extra work paid. Fill it in here and print it, or save it as a PDF.

Last reviewed by Estimark. This page states periods and rates set by statute or by standard contract terms. Those move, and this date is when somebody last read the page against its source rather than the day the site was built.

Fill it in here or print it blank. Nothing you type leaves this browser.

Variation Order

The contract

Numbered in sequence and never reused

The instruction

Most standard forms only recognise a variation instructed by the person the contract names, usually the contract administrator or the client. Record who gave it and when, even if it was given on site.

In writing, by email, or verbally on site and confirmed here
Addition, omission, substitution or a change in conditions

The price

Say how each line was valued: contract rates, adjusted rates, a fair rate, or dayworks where the work cannot be measured. A price with no basis is the first thing a client disputes.

ItemBasis of valuationQuantityRate (£)Amount (£)

The effect

None, or the number of working days and why

Agreement

Sign before the work starts where you can. A signature after the event is an argument about what was asked for.

No statute prescribes the form of a variation order. Your contract decides who may instruct a change, how it must be given and how it is valued.

In Estimark a variation is numbered and priced against the job, sent to the client for approval, and moves the budget when it is agreed, with the approval or rejection recorded with a reason and a time.

What should a variation order include?

A number, who instructed the change and when, what changed, how it was priced, what it does to the contract sum and the finish date, and both signatures.

  • Number variations in sequence so the final account can be reconciled against them one by one.
  • Record a verbal instruction the same day and send it back for signature. Work done on a spoken instruction is still usually payable, but proving it costs far more than writing it down.
  • Show the effect on time as well as money. A variation that adds a week of work and says nothing about the date is an extension of time given away.

How is a variation priced under a building contract?

In the order the contract sets: contract rates where the work is of a similar character, adjusted rates where it is similar but the conditions differ, a fair rate where nothing compares, and dayworks only where the work cannot be measured.

  • Write the basis beside each line, so the client checks the method rather than arguing the total.
  • JCT calls the change a variation. NEC calls it a compensation event and has its own notice periods, which are worth reading before the work starts.

This template follows common practice under the standard forms. Your own contract decides the procedure, and where it sets notice periods they apply whatever the paperwork looks like.

Common questions

What is a variation order in construction?
A written record of a change to the works instructed under the contract: an addition, an omission, a substitution or a change in the conditions of working. It states who instructed it, what changed, how it was priced and its effect on the contract sum and the completion date, and is signed by both parties.
Does a variation have to be in writing?
Most standard forms require variations to be instructed in writing by the person the contract names. A verbal instruction can still be enforceable, but the burden of proving it falls on the contractor, so confirm it in writing the same day.
Who can instruct a variation?
The person the contract names, usually the contract administrator, the architect or the client. An instruction from anybody else, such as a site visitor, is not an instruction under the contract until that person confirms it.