Payment
Final accounts: how to agree one without losing money
The short answer
The final account is the agreed statement of everything payable under the contract: the original sum, adjusted for variations, provisional sums, fluctuations, loss and expense, and any deductions. Once agreed and certified it settles the contract sum for good. Under JCT the final certificate is conclusive evidence on stated matters unless proceedings are started within 28 days of its issue, so the challenge window is short and easy to miss. The account is won by contemporaneous records rather than by argument, and by starting it during the job rather than after it.
At a glance
- Settles
- The contract sum, finally
- Includes
- Variations, provisional sums, loss and expense, deductions
- JCT challenge window
- 28 days from the final certificate
- After that
- Conclusive on the matters stated
- Triggered by
- Practical completion and the making good certificate
- Releases
- Any remaining retention
- Best defence
- Records made at the time
What goes into it?
- 01The original contract sum.
- 02Variations, valued under the contract rules. See variations in construction.
- 03Provisional sums, removed and replaced by the valuation of the work instructed. See provisional and PC sums.
- 04Prime cost sums, adjusted to actual cost, with profit adjusted and attendance usually not.
- 05Fluctuations, where the contract provides for them.
- 06Loss and expense, claimed and assessed under its own clause.
- 07Deductions. Liquidated damages, contra-charges, uncorrected defects.
- 08Retention, released in full once the making good certificate is issued.
Everything on that list should already exist as an agreed document. An account assembled from memory at the end is an account that will be argued line by line.
Free toolRetention calculatorWhat is still held, and the date the last of it becomes payable.Why does the 28-day window matter so much?
Because after it the final certificate becomes conclusive evidence on the matters the contract states, which usually include that the quality of work is to the satisfaction of the contract administrator where that was a matter for their opinion, and that all extensions and loss and expense have been given effect.
Conclusive means it cannot be reopened, even if it is wrong. Adjudication, arbitration or litigation must be commenced within the window to preserve the position.
Twenty-eight days from issue. Not from when somebody opened the envelope, and not from when the argument started.
NoteStarting an adjudication purely to stop the clock is a recognised and legitimate step where agreement is close but not reached. It preserves the right without ending the negotiation.
How do you actually get one agreed?
- 01Build it during the job. Every instruction valued and agreed as it happens, not saved up. An account agreed in pieces is agreed; one presented whole is negotiated.
- 02Agree the measure before arguing the rate. Two arguments at once settles neither.
- 03Close variations individually. A signed valuation on each is one fewer line in dispute at the end.
- 04Submit loss and expense with its substantiation. Timesheets, plant records, invoices. A prolongation claim with no records behind it is a number.
- 05Deal with deductions head on. Ask what is being deducted and on what basis, in writing, early.
- 06Set a meeting with authority in the room. Accounts settle when both people present can say yes.
The single largest factor is whether the records exist. Site diaries, signed daywork sheets, attendance records, delivery notes, photographs and correspondence, all made at the time, decide most of the disputed lines before anybody argues about them.
What is commonly lost?
| Item | Why it goes | What prevents it |
|---|---|---|
| Verbal variations | No written instruction | Confirm in writing the same day |
| Prolongation costs | No weekly prelim rates tendered | Split prelims fixed and time-related |
| Daywork | Sheets unsigned or late | Signed on the day, submitted weekly |
| Extension of time | Notice never given | Notify when the delay becomes apparent |
| Retention | Nobody chased the certificate | Diarise the end of the defects period |
| Attendance on PC sums | Priced at nil to look keen | Price it at tender |
Every row is a decision made months before the account is prepared. Almost nothing on that list can be recovered at the negotiation itself. The account is really settled during the job.
Questions
Frequently asked
How long do I have to challenge a final certificate?
Under JCT, 28 days from issue. Commence adjudication, arbitration or litigation within that window or the certificate becomes conclusive evidence on the matters the contract states, even where it is wrong.
When should the final account be submitted?
The contract sets a period, commonly within six months of practical completion under JCT. Check the clause, because a late submission can weaken a claim and in some forms lose it.
Can the final account be less than the contract sum?
Yes. Omitted work, unexpended provisional sums, liquidated damages and contra-charges all reduce it. A final account is an adjustment in both directions.
What if we cannot agree?
The contract administrator certifies what they consider due, and the dispute goes to adjudication if it cannot be settled. Adjudication is quick, and the 28-day conclusivity window makes starting it promptly important.
Does agreeing the final account release retention?
Retention is released on the certificate of making good at the end of the defects period, which is usually around the same time. The two are separate certificates and both need chasing.
Read next
What is retention, and how do you get it released?
Typical percentages, the two release points, and the notices that actually work.
What is a pay less notice?
Section 111, the deadline, and why a late notice means you pay the notified sum in full.
Applications for payment vs invoices
Two different documents with two different legal effects. Confusing them costs money.
Estimark: payment applications & retention
Construction Act dates, pay less deadlines and retention release on one screen.
Retention calculator
What is held, what the cap does to it, and the two dates the money comes back.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee.