What is a pay less notice, and when must it be served?
The short answer
A pay less notice is the notice a paying party must serve if it intends to pay less than the sum notified as due under a construction contract. It comes from section 111 of the Housing Grants, Construction and Regeneration Act 1996, as amended by the Local Democracy, Economic Development and Construction Act 2009. It must specify the sum the payer considers due at the date of the notice and the basis on which that sum is calculated, and it must be served before the deadline set by the contract — or, where the contract is silent, no later than seven days before the final date for payment. Serve it late, or not at all, and the notified sum becomes payable in full on the final date for payment.
At a glance
- Statute
- HGCRA 1996 s.111
- Amended by
- LDEDCA 2009
- Default deadline
- 7 days before final date for payment
- Must state
- Sum due and the basis of calculation
- Effect if late
- Notified sum payable in full
- Remedy for payee
- Smash-and-grab adjudication
- Right to suspend
- On 7 days’ written notice
How does the payment notice sequence work?
The Construction Act imposes a fixed sequence on every construction contract in the UK. Understanding it is what makes the pay less notice make sense.
- 01Due date. The contract must fix a date on which each payment becomes due. Section 110 requires an adequate mechanism for determining it.
- 02Payment notice. Within five days of the due date, the payer (or a specified person, such as a contract administrator) must serve a notice under section 110A stating the sum considered due and the basis of calculation. It must be served even if the sum is zero.
- 03Payee’s notice in default. If the payer serves nothing, the payee can serve its own notice under section 110B. Where the contract allows an application for payment before the due date, that application itself usually becomes the default notice.
- 04The notified sum. Whichever of those notices stands becomes the notified sum.
- 05Pay less notice. If the payer wants to pay less than the notified sum, it must serve a section 111 notice before the deadline.
- 06Final date for payment. The date the money must actually be paid. The contract sets the period between the due date and the final date.
Section 111: the payer must pay the notified sum on or before the final date for payment unless a valid pay less notice has been served.
When must a pay less notice be served?
By the deadline in the contract, which must be a fixed period before the final date for payment. Where the contract does not set one, or the term is not Act-compliant, the Scheme for Construction Contracts fills the gap: the notice must be given not later than seven days before the final date for payment.
The Scheme also supplies default dates for everything else if the contract is silent — a due date the later of seven days after the end of the relevant period or the making of the payee’s claim, and a final date for payment seventeen days after the due date. Most standard forms set their own dates, and those are the ones you have to diary.
| Contract | Typical pay less deadline |
|---|---|
| JCT Design and Build 2016/2024, interim payments | Not later than 5 days before the final date for payment |
| NEC4 Option A–F | The project manager’s assessment mechanism replaces most of it, but the Act still applies |
| Scheme for Construction Contracts (default) | Not later than 7 days before the final date for payment |
Always read the payment clause in the contract in front of you. These are the usual positions, not a substitute for the terms you signed.
NoteThe deadline runs backwards from the final date for payment, not forwards from the application. Change the final date and you change the pay less deadline with it.
What must a valid pay less notice contain?
Two things, and they are both mandatory: the sum the payer considers to be due at the date of the notice, and the basis on which that sum is calculated. A notice that gives a number without a basis is vulnerable; a notice that gives a basis without a number is not a notice.
- Identify the contract, the payment cycle and the application it responds to.
- State a specific figure as the sum considered due — including zero, if that is your case.
- Set out how you got there: valuation of the work, deductions for defects, contra-charges, liquidated damages, retention, previous payments.
- Serve it by a method the contract permits, to the person the contract names, and record the date and time it was sent.
The courts have been reasonably forgiving about form and reasonably unforgiving about substance and timing. A document does not have to be headed "Pay Less Notice" to be one, provided it makes clear what it is. But it does have to be in time, and it does have to give the figure and the basis.
A pay less notice must state a specific sum considered due and the basis of its calculation. An email saying "we dispute your application" is not a pay less notice.
What happens if the payer misses the deadline?
The notified sum becomes payable in full on the final date for payment, regardless of whether the work is worth it. The payee can start an adjudication to enforce payment of the notified sum — the so-called smash-and-grab adjudication — and the adjudicator is not asked to value the work. The only question is whether a valid notice was served in time.
The payer is not left without a remedy. Since the Court of Appeal’s decision in S&T v Grove, a payer who has had to pay a notified sum because it missed its notices can start a second, "true value" adjudication to establish what the work was actually worth and recover the difference. But it must pay first. The cash flow consequence lands immediately and the correction comes months later.
The payee also gains a separate right: under section 112, non-payment of a notified sum by the final date entitles the payee to suspend performance of any or all of its obligations, on seven days’ written notice, and to recover the reasonable costs of suspending and remobilising along with an extension of time.
Does the Construction Act apply to my contract?
It applies to contracts for construction operations in the UK, whether written or oral since the 2009 amendments removed the requirement for writing. It is not optional and it cannot be contracted out of — a non-compliant clause is simply replaced by the Scheme.
The main exclusions are:
- Residential occupiers. A contract with someone who occupies, or will occupy, the dwelling as their residence is excluded by section 106. Domestic extension work for a homeowner is outside the Act.
- Excluded operations. Drilling for oil or gas, mineral extraction, and the manufacture or delivery to site of components and materials, among others.
- Contracts of employment, and some finance and development agreements.
NoteThe residential occupier exclusion is why a domestic builder cannot adjudicate against a homeowner unless the contract gives that right expressly. It also means the payment notice regime does not apply — you rely on your own payment terms and, if necessary, the county court.
How does Estimark help with the dates?
Payment applications in Estimark carry the Construction Act dates — the due date, the final date for payment and the pay less deadline — on the application itself, so the deadline sits next to the document it applies to rather than in someone’s diary. Certified applications become invoices, and the VAT reverse charge treatment carries through to them.
It is a record, not a lawyer. Estimark does not serve notices for you, does not assess whether a notice you received is valid, and does not advise on contract terms. Read more about payment applications and retention in Estimark.
Questions
Frequently asked
What is a pay less notice?
A notice under section 111 of the Housing Grants, Construction and Regeneration Act 1996 that a paying party must serve if it intends to pay less than the sum notified as due. It must specify the sum the payer considers due at the date of the notice and the basis on which that sum is calculated.
When must a pay less notice be served?
By the deadline in the contract, which must be a set period before the final date for payment. If the contract is silent or non-compliant, the Scheme for Construction Contracts applies and the notice must be given no later than seven days before the final date for payment. JCT Design and Build sets five days for interim payments.
What happens if a pay less notice is late?
The notified sum becomes payable in full on the final date for payment, whatever the work was actually worth. The payee can enforce it by adjudication, and the payer can only recover any overpayment afterwards through a separate true value adjudication — after it has paid.
Does a pay less notice have to be called a pay less notice?
No. The courts look at substance. A document that clearly states the sum considered due and the basis of its calculation, served in time and by a permitted method, can be a valid pay less notice without that heading. Titling it correctly removes an argument, so title it correctly.
Can I stop work if I am not paid the notified sum?
Yes. Section 112 gives the payee a right to suspend performance of any or all obligations where a notified sum is not paid by the final date for payment, on seven days’ written notice. You can recover reasonable costs of suspension and remobilisation and are entitled to an extension of time.
Read next
Applications for payment vs invoices
Two different documents with two different legal effects. Confusing them costs money.
What is retention, and how do you get it released?
Typical percentages, the two release points, and the notices that actually work.
Getting paid faster
Quoting, invoicing and chasing — plus the statutory interest most firms never claim.
Estimark — payment applications & retention
Construction Act dates, pay less deadlines and retention release on one screen.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. Fourteen days, full access, no implementation fee.