Estimating

How to do a quantity take-off from drawings

11 min read

The short answer

A quantity take-off is the measurement of the work shown on the drawings, item by item, in the units it will be priced in. Work from the current revision of the drawings, with the specification and structural drawings beside you. Use figured dimensions wherever they exist, and scale only when you must, after checking the scale against a figured dimension. Measure net, as the work will be fixed in position, and leave waste, laps and bulking to the rate: that is the rule in NRM2, the RICS New Rules of Measurement for detailed measurement of building works. Measure in the order the building goes up, take walls on their centre line, deduct the openings, and record the drawing number and revision against the take-off so a revised drawing can be re-measured.

At a glance

Units
m, m², m³ and nr, with t or kg for steel
Measure
Net, as fixed in position (NRM2 3.2.1)
Waste and laps
In the rate, not the quantity
Dimensions
To the nearest 10 mm under NRM2
Walls
On the centre line
Masonry voids
Not deducted at 0.50 m² or less
Figured or scaled
Figured dimensions win
Current standard
NRM2 2nd edition, from 1 December 2021

What is a take-off, and what do you need before you start?

A take-off turns drawings into quantities: so many cubic metres of excavation, square metres of blockwork, metres of skirting and number of doors. The quantities are what you price, so a mistake here goes straight into the quote. Before you measure anything, gather these.

  • The current revision of every drawing. Check the drawing register or the title blocks, and set aside anything superseded. Note each drawing number and revision letter on the take-off.
  • Building Regulations drawings, not only planning drawings. Planning drawings show the outside; the construction drawings show foundation depths, wall build-ups and floor and roof construction.
  • The structural drawings and calculations. Steel sizes, padstones, lintels and the foundation design come from the engineer.
  • The specification. It tells you what each measured item is made of, and so what rate it takes.
  • Door and window schedules, where there are any. A count from the schedule checks your count from the plans.

Where something is missing or the drawings disagree, raise a question with the designer and note the assumption you measured on. A take-off built on an unwritten assumption cannot be defended when the quantity is challenged.

How do you read the scale on a drawing?

A scale of 1:50 means one unit on the drawing is fifty on site. Plans and elevations for domestic work are usually 1:50 or 1:100, details 1:20, 1:10 or 1:5, and location plans much smaller. The scale is stated in the title block together with the paper size it applies to, such as ‘1:50 at A1’.

Scale10 mm on the drawing is1 metre on site is
1:550 mm200 mm on paper
1:20200 mm50 mm on paper
1:50500 mm20 mm on paper
1:1001 metre10 mm on paper
  • The paper size matters. A drawing that is 1:50 at A1 is 1:100 when printed on A3, because A3 is half the length and width of A1.
  • A scale bar survives resizing. It shrinks and grows with the drawing, so it stays true when the stated scale does not.
  • ‘Do not scale’ means it. The note tells you the designer will stand behind the figured dimensions and not behind anything measured off the sheet.

Figured dimensions win. Where a written dimension and a scaled one disagree, measure to the written one and ask about the gap. Scale only where nothing is figured, and record that you did.

How do you measure from a PDF without getting the scale wrong?

Most drawings now arrive as PDFs, and the PDF knows nothing about the scale. Whether you print it or view it, the drill is the same.

  1. 01Print at actual size on the stated paper size. ‘Fit to page’ or ‘shrink to printable area’ changes the scale by a few per cent, enough to ruin every quantity without looking wrong.
  2. 02Check against a figured dimension before measuring anything. Pick the longest written dimension on the sheet and scale it. If it does not agree, find out why before you go on.
  3. 03Check both directions. A scanned drawing can be stretched in one direction and not the other.
  4. 04Write the check down. ‘Checked 1:50 at A1 against the 6,000 mm rear wall dimension’ on the take-off tells the next person the scale was tested.
  5. 05Check again on each new sheet and revision. Different sheets can be at different scales, and a revision can be issued at a different size.

What units and rules should you measure to?

Measure each item in the unit it will be priced in: metres (m) for runs such as skirting, DPC and lintels, square metres (m²) for walls, floors, ceilings and roofs, cubic metres (m³) for excavation and concrete, and number (nr) for doors, windows and fittings. Reinforcement goes by weight.

NRM2 is the RICS New Rules of Measurement for detailed measurement of building works, used to prepare bills of quantities. The current edition is the 2nd, published in October 2021 and effective from 1 December 2021, reissued in October 2022 as RICS practice information. You are not obliged to follow it on your own take-off, but its rules are the ones a quantity surveyor is likely to measure against.

NRM2: measure work net as fixed in position, unless otherwise stated. Laps, joints, waste and cutting are allowed for in the rate, not added to the quantity.

  • Dimensions to the nearest 10 mm. A bill gives quantities to the nearest whole unit; keep the decimals in your own workings.
  • Excavation is the hole, not the spoil. NRM2 measures excavation as the bulk before digging, with no allowance for the spoil bulking up or for working space. Allow for both in the rate and the muck-away.
  • Walls on the centre line. NRM2 measures all walling on the centre line, whatever the construction.
  • Deduct openings. Openings at the edge of a measured area are always deducted, and in masonry a void of half a square metre or less is not deducted. Doors and windows are bigger than that, so they come out.

Your units must match the units your rates are in. A schedule of rates prices per unit of measured work, so a quantity in the wrong unit prices the wrong job.

Free toolUK construction glossaryGirth, nr, provisional sum, preliminaries and the rest of the vocabulary, defined in a sentence each.

In what order should you measure?

In the order the building goes up, so nothing is skipped and each item follows from the last. NRM2’s work sections run in broadly the same order.

  1. 01Demolition, site clearance and preparation.
  2. 02Substructure: excavation, disposal, foundations, walls to DPC, ground floor.
  3. 03Drainage below ground.
  4. 04Superstructure: external and internal walls, lintels, frame.
  5. 05Upper floors and roof: structure, coverings, rainwater goods.
  6. 06Windows, external doors and the openings for them.
  7. 07Internal joinery, partitions and doors.
  8. 08Finishes: plaster, screed, floor, wall and ceiling finishes, decoration.
  9. 09Services and fittings.
  10. 10External works.

Preliminaries are priced from the programme rather than measured from the drawings: see preliminaries and how to price them.

How do centre-line girths and deductions work?

The girth is the length of a wall run. Measured along the outside face, it overstates the wall, because at every external corner the outside face is longer than the centre line. Measured along the inside face, it understates it. The centre line is the true length of wall material, and it is also the line most strip foundations are centred on.

Centre-line girth = external girth less, for each external corner, twice the distance from the outside face to the centre line. For a whole wall that is one wall thickness per corner.

A closed rectangle has four corners. An extension built against the house usually has two, because the flank walls stop at the existing wall. For a cavity wall, each leaf has its own centre line, so the inner leaf takes a bigger corner adjustment than the whole wall.

Measure the wall gross, centre-line girth times height, then deduct each opening that qualifies. Keep the deductions as separate lines so they can be checked, and pick up what the openings add: lintels, cavity closers, sills and reveals, each as its own item.

Can you show me a worked example?

A single-storey rear extension, 4.000 m from the house and 6.000 m wide to the outside faces. The cavity wall is 300 mm overall: a 100 mm outer leaf, a 100 mm cavity and a 100 mm block inner leaf. The strip foundation trench is 600 mm wide and 1.000 m deep, with 225 mm of concrete in the bottom. The rear wall has a bifold door opening and one flank wall has a window. The design is made up for the example; this is the arithmetic for two items. For pricing the rest of the job, see how to price a house extension.

ItemWorkingQuantity
External girth, three new walls4.000 + 6.000 + 4.00014.000 m
Less two corners, whole wall2 × 2 × 0.150−0.600 m
Centre-line girth, foundations13.400 m
Trench excavation13.400 × 0.600 × 1.0008.040 m³
Concrete in foundations13.400 × 0.600 × 0.2251.809 m³
Inner leaf centre-line girth14.000 less 2 × 2 × 0.25013.000 m
Blockwork inner leaf, gross13.000 × 2.400 high31.200 m²
Less bifold opening3.000 × 2.100−6.300 m²
Less window opening1.200 × 1.050−1.260 m²
Blockwork inner leaf, net23.640 m²

Illustrative figures for a worked example, not a real design. The inner leaf’s centre line is 250 mm in from the outside face.

Check the girth a second way. Each flank wall runs 4.000 m less half the rear wall’s thickness, 3.850 m, and the rear wall runs between the flank centre lines, 6.000 m less 0.300 m. Two flanks at 3.850 m plus 5.700 m is 13.400 m, the same answer. Both openings are well over half a square metre, so both come out of the blockwork.

NoteMeasured on the outside face, the trench would be 14.000 m long and the excavation 8.400 m³, about 4.5% too much. On a bigger building with more corners the error grows, and it compounds through excavation, concrete, walling and muck-away.

What checks catch take-off errors?

  • Re-do the arithmetic. Multiplying out the dimensions, traditionally called squaring, is where slips hide. Check every product, ideally by somebody else.
  • Measure one thing two ways. Girth from the outside less corners, and girth from its parts, as in the example.
  • Cross-check related totals. Floor finish against the floor area, skirting against the room perimeters less door openings, plaster against the inside wall area, door count against the schedule.
  • Compare with a similar job. Blockwork per square metre of floor, or concrete per metre of trench. A figure far off your usual range is usually a misplaced decimal or a missed item.
  • Have a second person check it. Somebody who did not measure it reads the drawings fresh and spots the omission you cannot see.
  • Keep the take-off with its drawing revision. When revision C arrives, re-measure only what the revision clouds and notes changed, and note the new revision against those items.

Then price it. Quantities are only the first half of an estimate: see how to price a job properly.

How does Estimark hold a take-off?

In Estimark a take-off is an estimate, under Take-offs in the menu. Upload the drawings and each page becomes a sheet, with its scale read from the title block where one is printed, or set by clicking two points a known distance apart. The tools measure on the sheet at that scale: a length, an area with openings deducted, a rectangle, a count, a wall area from a length and a height, and a volume from an area and a depth. Each measurement becomes a line in the bill with its working, and dragging its points measures it again. Put the drawing number and revision in the estimate’s title.

Each line is priced from your own price book, assemblies and labour rates, and a line with none is marked No rate. When the take-off is done, Send to quote puts the priced lines on a new quote or an existing one, by section. A line with no rate is held back unless you ask for it as a flagged line at nil, so read down the bill before it goes. The drawings can also be read by the AI, which proposes the lines for you to check: see AI take-off from drawings, and tenders and estimating.

Sources

Questions

Frequently asked

How is a take-off different from a bill of quantities?

A take-off is the measurement. A bill of quantities is the priced or pricing document built from it, with each item described and quantified to a standard such as NRM2 so that every tenderer prices the same thing.

Should I add waste to the quantities?

No. Measure net, as fixed in position, and put the waste allowance in the rate. NRM2 works that way, and it keeps the quantity checkable against the drawing.

Can I scale from a drawing marked ‘do not scale’?

Only where there is no figured dimension, and only after checking the scale against one that is figured. Record that the quantity was scaled and raise a question with the designer, because the note means they will not stand behind a scaled dimension.

Which version of NRM2 is current?

The 2nd edition, published by RICS in October 2021 and effective from 1 December 2021. It was reissued in October 2022 as RICS practice information with no material change to its content.

Why measure walls on the centre line?

Because it is the true length of wall material. The outside face overstates the length at every external corner and the inside face understates it. NRM2 measures all walling on the centre line.

What do I do when a revised drawing arrives?

Compare it with the revision you measured, re-measure the items the revision changed, and record the new revision against them. Keeping the drawing number and revision on the take-off is what makes this possible.