Health & Safety
What should a site induction cover?
The short answer
A site induction is the briefing every worker gets before starting on a particular site, covering that site’s rules, hazards and emergency arrangements. Under regulation 13(4)(a) of the Construction (Design and Management) Regulations 2015, the principal contractor must ensure a suitable site induction is provided. Under regulation 15(9)(a), every contractor must give its own workers one where the principal contractor has not, so on a single-contractor job the contractor always does it. HSE’s guidance says it should be site specific and cover the project, how it is managed, first aid, accident reporting, ongoing briefings, consultation and each worker’s own responsibilities. In practice that means the site rules, this site’s hazards, emergency and welfare arrangements, permits, PPE, asbestos and traffic routes, given before work starts, checked for understanding and recorded.
At a glance
- Principal contractor duty
- CDM 2015 reg 13(4)(a)
- Contractor duty
- CDM 2015 reg 15(8) and (9)(a)
- HSE guidance
- L153, paragraphs 133 and 134
- Applies to
- Every construction site in Great Britain, domestic jobs included
- Information must be
- Comprehensible, as soon as practicable (reg 8(6))
- Visitors
- Inducted in proportion to the visit
- Repeat it
- When the risks change (MHSWR 1999 reg 13)
- Signed record
- Not required by law; how you show it happened
Who has to give a site induction?
Two regulations in CDM 2015 put the duty in place, and between them they cover every construction site in Great Britain.
- The principal contractor must ensure that a suitable site induction is provided, under regulation 13(4)(a). On a job with more than one contractor, the induction to the site is the principal contractor’s to organise.
- Every contractor must give each worker under its control the supervision, instructions and information to work safely, under regulation 15(8). Regulation 15(9) says that information must include a suitable site induction where the principal contractor has not already provided one, the procedures for serious and imminent danger, and the risks from its own risk assessment and from other contractors’ work.
On a job with one contractor there is no principal contractor, so the contractor gives the induction. On a job with several, the principal contractor ensures one is given, and each contractor fills any gap for its own people.
The Management of Health and Safety at Work Regulations 1999 add to this. Regulation 13(2) requires training for employees when they are recruited and when they are exposed to new or increased risks, and regulation 12(3) requires an employer to give anyone working in its undertaking who is not its employee, a subcontractor’s operative for instance, appropriate instructions and comprehensible information about the risks.
NoteNorthern Ireland has its own Construction (Design and Management) Regulations (Northern Ireland) 2016. The duties below are the Great Britain ones.
What does HSE say an induction should cover?
HSE’s guidance on CDM 2015, L153, says the induction should be site specific and highlight the particular risks and controls that people working on the project need to know about. It lists eight topics to consider:
- 01Senior management commitment to health and safety.
- 02An outline of the project.
- 03How the project is managed.
- 04First-aid arrangements.
- 05Accident and incident reporting arrangements.
- 06Arrangements for briefing workers on an ongoing basis, such as toolbox talks.
- 07Arrangements for consulting the workforce on health and safety.
- 08Each worker’s own responsibility for health and safety.
The site rules come from the construction phase plan, which regulation 12(2) requires to set out the health and safety arrangements and site rules. HSE’s list of what site rules usually cover is PPE, radios and mobile phones, smoking, restricted areas, hot works, traffic management, pedestrian routes, site tidiness, fire prevention, permits to work and emergency arrangements. It adds that the rules should be clear, easily understood and brought to the attention of everyone on site. The induction is where that happens.
What should you cover on the day?
A checklist built from L153, regulation 15(9) and HSE’s site rules list. Leave out what does not apply to the site and add what does: an induction that covers confined spaces on a loft conversion has not been written for that site.
- 01Who is who. The site manager, the supervisor, the first aiders, the fire marshal, and who each person reports to.
- 02The job. What is being built, the programme, and where the work is this week.
- 03Site rules. Hours, access and signing in, smoking, phones, tidiness, restricted areas.
- 04This site’s hazards. Scaffold, excavations, live services, work at height, an occupied house, neighbours and the public, and the controls for each.
- 05Asbestos. What the survey found, where it is, and that anyone who uncovers suspect material stops work and reports it. See which asbestos survey the work needs.
- 06Emergencies. The alarm, escape routes, the assembly point, fire points, and the rule for serious and imminent danger: stop work, report it, go to a place of safety.
- 07First aid. Who the first aiders are, where the kit is, and the nearest A&E.
- 08Welfare. Toilets, washing, drinking water, the drying room and where to eat. See Welfare facilities on a construction site.
- 09Reporting. Accidents, near misses and anything unsafe, and to whom. Regulation 8(5) requires anyone working under another’s control to report anything likely to endanger themselves or others.
- 10Permits. Which work needs one, such as hot work, confined spaces or work on services, and who issues them.
- 11PPE. What is required where, how it is issued and how it is replaced. See PPE on site: what the 2022 regulations changed.
- 12Traffic. Pedestrian routes, vehicle routes, the delivery area, and who directs vehicles.
- 13Their task. Which RAMS covers their work, briefed and signed against the current version. See what a RAMS must contain.
- 14Ongoing briefings and consultation. When toolbox talks happen and how to raise a concern.
How do you check the induction has been understood?
Regulation 8(6) of CDM 2015 requires information and instruction to be comprehensible and provided as soon as practicable, and regulation 10 of the 1999 Regulations asks for comprehensible information too. L153 says information should be in simple, clear English and other languages where appropriate, in a logical order, with photographs or diagrams where they help, and given before the work begins.
HSE’s guidance on new workers is blunt about why this matters: workers are as likely to have an accident in their first six months at work as during the whole of the rest of their working life. It says to use plain language and photos of hazards, and to check that people have understood and are acting on what they were told.
- Ask, do not tell. “Where is the assembly point?” tests more than “Any questions?”
- Walk it. Show the routes, the welfare, the fire point and the restricted areas on the ground.
- Use an interpreter or a translated sheet where someone’s English is not good enough to follow the briefing, and record that you did.
- Watch the first hour. A supervisor who sees someone on the wrong route has found a gap in the induction, not only in the person.
Do visitors and delivery drivers need an induction?
Visitors do, in proportion to the visit. L153 says inductions should also be given to people who visit occasionally, such as architects, or once only, such as students. An escorted visitor only needs to know the main hazards they may meet and the controls; an unescorted visitor needs more. The principal contractor’s duty to stop unauthorised access under regulation 13(4)(b) is the reason the gate needs to know who they are.
Delivery drivers are a traffic risk as much as a visitor. HSE’s construction guidance says to give induction training to drivers, workers and visitors and to send instructions to visitors before they arrive. Its guidance on deliveries lists what a visiting driver should know:
- Where to park on arrival, and where and to whom to report.
- A site plan or sketch showing the route through the site and the unloading area.
- Any restriction on the size or type of vehicle the site can take.
- The procedures to follow, such as wearing hi-vis, limits on mobile phones and any ban on reversing.
- Where to stand while the vehicle is unloaded. HSE notes drivers are often the victims of delivery accidents.
Send this to the supplier with the order and the briefing at the gate is short. HSE adds that people who direct vehicle movements must be trained and authorised to do it.
Does a small or domestic job need an induction?
Yes. CDM 2015 applies to construction work on every project in Great Britain, and HSE’s guidance is that a contractor’s role on a domestic job is no different from its role on a commercial one: regulations 8 and 15 apply in proportion to the risks. What changes for a homeowner client is that the client’s duties pass to the contractor or principal contractor under regulation 7. See when CDM applies and what the F10 is for.
Proportionate is the point. On a two-person bathroom refit the induction may be ten minutes at the front door: who is in charge, the household’s rules, where the stopcock and consumer unit are, where the asbestos survey says not to drill, where to eat and wash, and what to do if something goes wrong. It still needs to happen before work starts, and it still needs a record.
When does an induction need repeating?
When the site changes enough that the first one is out of date. Regulation 13 of the 1999 Regulations requires training when people are exposed to new or increased risks, including a new system of work or new work equipment, and says it must be repeated periodically where appropriate, adapted to new or changed risks, and given in working hours. Regulation 12(4) of CDM 2015 requires the construction phase plan to be reviewed and revised as the work goes on, and a revised plan is a reason to re-brief.
- A new phase: the scaffold goes up, the roof comes off, the excavation opens.
- A change to the emergency route, the assembly point or where the welfare is.
- A new hazard: a service found, asbestos uncovered, a neighbouring operation starting.
- After an incident or a near miss that showed the induction had a gap.
- Someone returning after long enough away that the site has moved on.
Small changes go in a toolbox talk rather than a full re-induction. A validity date on each induction record makes sure the larger ones are not forgotten.
What record should you keep of a site induction?
No regulation requires the induction to be signed. But you have to be able to show it happened, and after an incident the first question is what the injured person had been told. A record made on the day, signed by the person inducted, answers it.
- The person’s name, employer and role.
- The date, and who gave the induction.
- The topics covered, and any language support given.
- The person’s signature.
- A valid-until date, or the event that ends it.
How does Estimark record site inductions?
In health and safety, each induction records who was inducted and for which company, who delivered it, the topics covered, a signature and a valid-until date, so inductions run out instead of lasting forever. An induction can be for one job or company-wide, covering every site. Toolbox talks sit beside it with a signed attendance list.
At the gate, QR site attendance can check a clock-on for an induction that is still valid today, job-specific or company-wide, alongside an in-date CSCS card and acceptance of the current RAMS. Each check is set to off, warn or block for that job and ships switched off. The scan page needs no login, so a subcontractor’s operative can accept the current RAMS there.
Sources
- Construction (Design and Management) Regulations 2015, regulation 13 (legislation.gov.uk)
- Construction (Design and Management) Regulations 2015, regulation 15 (legislation.gov.uk)
- Construction (Design and Management) Regulations 2015, regulation 8 (legislation.gov.uk)
- Managing health and safety in construction, L153 (HSE)
- Management of Health and Safety at Work Regulations 1999, regulation 13 (legislation.gov.uk)
- Management of Health and Safety at Work Regulations 1999, regulation 12 (legislation.gov.uk)
- Site rules and induction (HSE)
- Traffic management on site (HSE)
- Delivering safely (HSE)
- New to the job (HSE)
- Construction (Design and Management) Regulations (Northern Ireland) 2016 (legislation.gov.uk)
Questions
Frequently asked
Is a site induction a legal requirement?
Yes. Regulation 13(4)(a) of CDM 2015 requires the principal contractor to ensure a suitable site induction is provided, and regulation 15(9)(a) requires every contractor to give its own workers one where the principal contractor has not. It applies to every construction site in Great Britain, domestic jobs included.
Who should give the site induction?
Someone who knows the site, its rules and its hazards, usually the site manager or supervisor. The duty sits with the principal contractor where there is one, and with the contractor on a single-contractor job.
Does someone already inducted on another of my sites need a new induction?
Yes, for the site-specific part. HSE’s guidance is that the induction should be site specific and cover that site’s particular risks. Company rules can be covered once, but the hazards, routes, emergency arrangements and welfare differ from site to site.
Do visitors need a site induction?
Yes, in proportion to the visit. HSE’s L153 says escorted visitors only need to know the main hazards they may meet and the controls, while unescorted visitors need more detail. Delivery drivers should be told where to park, where to report, the route and where to stand during unloading.
Does a site induction have to be signed?
No regulation requires a signature. But you need to be able to show the induction was given and what it covered, and a record made on the day and signed by the person inducted is how you do that.
How often should site inductions be refreshed?
There is no fixed interval. Re-brief when the risks change: a new phase of work, a new hazard, a change to the emergency or welfare arrangements, or after an incident. The 1999 Management Regulations require training to be repeated periodically where appropriate and adapted to new or changed risks.
Read next
CDM 2015: when do I notify HSE on an F10?
The two thresholds, who notifies, and the duties that apply whether you notify or not.
Construction phase plan: who writes it, and when is it required?
Required on every construction project, and the place the site rules are written down.
Toolbox talks: what the law asks for and what makes one work
No regulation uses the phrase. The duty behind it is statutory, and the attendance record proves you met it.
Estimark: health and safety
Versioned RAMS signed per operative, inductions that expire, toolbox talks, near misses and permits to work.
Toolbox talk record template
Subject, key points, actions and the signed attendance register that evidences it.
RAMS template
Risk assessment, method statement, emergency arrangements and a signed briefing record.
Estimark pricing
Solo £39 +VAT, Core £129 +VAT and Pro £299 +VAT a month plus seats, Enterprise quoted. 14-day free trial.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee and no card needed.