Building control completion certificates: how to get one and why it matters
The short answer
A completion certificate is the document a local authority gives under regulation 17 of the Building Regulations 2010 once it is satisfied, after taking all reasonable steps, that finished building work meets the requirements. In England it follows the completion notice the person carrying out the work must give within five days of finishing, and the authority has eight weeks from receiving that notice. A registered building control approver gives a final certificate to the local authority instead, and an installer in a competent person scheme gives the occupier a compliance certificate within 30 days. Each is evidence of compliance, not conclusive proof. GOV.UK warns that without the certificates a homeowner may struggle when selling. Work done without approval can be put right through a regularisation certificate from the local authority under regulation 18, for work carried out on or after 11 November 1985.
At a glance
- Notice before starting
- At least 2 days (reg 16(1))
- Commencement notice
- Within 5 days of commencing (reg 16(3C))
- Completion notice
- Within 5 days of completion (reg 16(4))
- Completion certificate
- Within 8 weeks of that notice (reg 17(2))
- Approver’s final certificate
- Council may reject within 10 working days
- Competent person scheme
- Certificate expected within 8 weeks (GOV.UK)
- Regularisation
- Work on or after 11 November 1985 (reg 18)
- Removal notice
- Up to 10 years after completion (BA 1984 s.36)
What is a completion certificate, and who issues it?
It is the building control body’s statement that, as far as it could establish, the finished work meets the Building Regulations. Under regulation 17 a local authority must give one where it is satisfied, after taking all reasonable steps, that the relevant requirements have been met. The certificate is evidence, but not conclusive evidence, that they have been, and it has to say so on its face.
The document the homeowner ends up with depends on who checked the work. Higher-risk buildings go to the Building Safety Regulator and are outside the scope of an extension or loft.
| Route | Who checks the work | Document at the end | Legal basis |
|---|---|---|---|
| Full plans or building notice | The local authority | Completion certificate | Building Regulations 2010, reg 17 |
| Registered building control approver | A private approver, after an initial notice to the council | Final certificate, given to the local authority | Building Act 1984, s.51 |
| Competent person scheme | The registered installer | Building Regulations compliance certificate | Building Regulations 2010, reg 20 |
| Work done without approval | The local authority, afterwards | Regularisation certificate | Building Regulations 2010, reg 18 |
England. Private building control is carried out by registered building control approvers, under regulations in force since 6 April 2024.
A completion certificate is not the same as practical completion. One is the regulator’s view of compliance; the other is the contract’s view of whether the job is finished.
Both belong in the handover file. See what is practical completion, and who decides it?
Which building control route should the job use?
The route is chosen before work starts, and the certificate at the end comes from whoever was chosen.
- Full plans. Plans are checked before work starts. GOV.UK says to expect a decision within 5 weeks, or 2 months with consent. Full plans are compulsory for work on a building the Fire Safety Order applies to, a new building fronting a private street, and work over or near a drain or sewer shown on the sewer map, which requirement H4 covers (regulation 12(3) to (5)).
- Building notice. GOV.UK says it is only for smaller projects and work can start 2 days after the notice is given. There is no plan approval, so the inspector’s requirements arrive on site.
- Registered building control approver. The approver gives the council an initial notice and then does the checking.
- Competent person scheme. For specific kinds of work, such as electrics or a boiler, a registered installer self-certifies under regulation 12(6)(a) and Schedule 3, and no building control application is needed for that work.
A full plans approval lapses if the work has not commenced within 3 years (Building Act 1984, section 32). It also gives one protection a building notice does not: the council cannot serve a section 36 notice on work built in line with the approved plans and any requirements it set (section 36(5) and (5A)).
Which notices does the person doing the work have to give?
On the local authority route, regulation 16 puts the notices on the person carrying out the work, which on most domestic jobs is you. The start, stage, commencement and completion notices apply only where regulation 12 requires a building notice or full plans, so not to work done under a competent person scheme.
| Notice | When | Regulation 16 |
|---|---|---|
| Intention to start work | At least two days before starting | (1) |
| Specified stages | When the authority asks, at stages it intends to inspect, with any period the work must stay uncovered | (3) to (3B) |
| Commencement | Within five days of the work being regarded as commenced | (3C) |
| Completion of remedial work | Within a reasonable time after correcting work the authority found in breach | (7) |
| Completion | Within five days of completion, with the statements in (4A) | (4), (4A) |
England, local authority route.
What counts as commenced is set by regulation 46A. For an extension, it is when the sub-surface structure, including all foundations and the structure of the ground floor, is completed. The authority can reject a commencement notice within four weeks, with reasons, and the person who gave it can appeal to the First-tier Tribunal within 21 relevant days.
With an approver, the notices go to the approver under regulation 15 of the Building (Registered Building Control Approvers etc.) (England) Regulations 2024: at least two working days before starting, and within five working days of commencement. For building the notices into a programme, see how to build a construction programme for a small job.
What must the completion notice contain, and who signs it?
Since 1 October 2023 in England, the completion notice is a set of declarations, not a phone call to say you have finished. Regulation 16(4A) requires:
- the name, address, phone number and email address (if any) of the client;
- the same details for the principal contractor or sole contractor, and the principal designer or sole or lead designer;
- a statement that the building work is complete;
- a statement signed by the client confirming that, to the best of their knowledge, the work complies with all applicable requirements of the Building Regulations;
- a signed statement from each principal contractor (or sole contractor) and each principal designer (or sole or lead designer), giving their details, the dates of their appointment, and confirmation that they fulfilled their duties under Part 2A.
On a domestic job with one contractor, regulation 11C gives the client’s Part 2A duties to that contractor, and the contractor signs the contractor’s statement. The homeowner still signs the client’s statement. Since 7 October 2025, where a dutyholder’s statement cannot be obtained, the notice must give the reasons instead (regulation 16(4B)).
Collect the designer’s contact details and appointment dates at the start of the job. Chasing a designer who left the project months ago is how a completion notice misses its five days.
On the approver route, regulation 18 of the 2024 Regulations requires the client to give the approver the same set of declarations when the work is complete.
How do you get from the first notice to the certificate?
A single-storey extension on the full plans route, from start to certificate:
- 01Apply. The client, or their designer, makes the full plans application, and you agree who will give the notices.
- 02Get the decision. Check any conditions the approval carries against your price.
- 03Give notice of intention to start at least two days before work begins.
- 04Note the inspection stages the authority specifies, and do not cover up work it has said must stay open.
- 05Give the commencement notice within five days of the foundations and ground floor structure being complete.
- 06Build to the approved plans. Where the authority says work does not comply, correct it and tell them when it is done.
- 07Collect the scheme certificates. Electrics, heating and windows installed by registered installers come with their own certificates, which GOV.UK says to expect within 8 weeks of completion. The installer must notify building control within 30 days (regulation 20(3)).
- 08Give the completion notice within five days of finishing, with the signed statements.
- 09Receive the completion certificate. The authority has eight weeks from receiving the completion notice to give it, where satisfied (regulation 17(2)).
- 10Hand over. Put the completion certificate, the scheme certificates and the approved plans in the handover file.
Run the snagging list alongside, so the certificate and the agreed snags reach the client together. See what is a snagging list, and what makes one hold up? The electrical side is covered in Part P: which electrical work must be notified?
What happens if there is no completion certificate?
For the homeowner, the problem shows up at sale. GOV.UK says that without approval they will not have the certificates of compliance they may need when they sell, and that a competent person scheme certificate shows up in solicitors’ searches.
For whoever did the work, the exposure is legal.
- Prosecution. Contravening the Building Regulations is an offence under section 35 of the Building Act 1984, punishable by a fine, imprisonment or both, with up to two years’ imprisonment on conviction in the Crown Court.
- Removal or alteration. Under section 36 the authority can require the owner to pull down or alter non-compliant work, and do it themselves and recover the cost if the owner has not complied within 28 days. The notice can be given up to 10 years after the work was completed.
- Laying open. Where the notices were not given, regulation 16(6) lets the authority require work to be cut into, laid open or pulled down so it can see whether it complies.
NoteA missing notice of intention to start can make otherwise approved work ‘unauthorised building work’ under regulation 18(8). Full plans approval does not cover for a notice nobody gave.
How does regularisation work for work done without approval?
Regularisation is retrospective approval, available only from the local authority and only for work carried out on or after 11 November 1985. The owner applies under regulation 18.
- 01Apply in writing, stating the application is under regulation 18, with a description of the work and, so far as reasonably practicable, a plan of it and a plan of any work needed to make it comply.
- 02Take the steps the authority asks for, which can include laying the work open, testing and taking samples.
- 03The authority says what work it thinks is needed, that it cannot tell, or that none is needed.
- 04Once satisfied, it may give a regularisation certificate. Like a completion certificate, it is evidence but not conclusive evidence.
The work is judged against the regulations that applied when it was done, not today’s. For a builder asked to put right a previous contractor’s unapproved extension, price the opening up and the remedial work as provisional, because nobody knows the answer until the authority has looked.
Free toolUK construction glossaryFull plans, building notice, regularisation and practical completion, each defined in a sentence.What is different in Wales, Scotland and Northern Ireland?
Wales uses the same 2010 Regulations, with its own versions of many of them. On 1 July 2026 the Building etc. (Amendment) (No. 2) (Wales) Regulations 2025 rewrote the Welsh regulation 16. The Welsh rules now call the local authority the building control authority, and require:
- notice at least two days before starting, as in England;
- notice before covering up foundation excavations, foundations, the damp-proof course, oversite concrete or drains, with at least one day elapsed;
- notice within five days after laying, haunching or covering a drain or sewer;
- a commencement notice within 5 days, with any challenge going to the magistrates’ court rather than a tribunal;
- a completion notice within five days, with dutyholder declarations under the Welsh rules in Part 2B and a client statement, which an applicant can sign on the client’s behalf if the client declares their approval.
In Wales a domestic client can take on the client duties themselves, or give them to another person, by a signed written statement (regulation 11T). The certificate period stays at 8 weeks from the completion notice.
Scotland runs a building warrant system under the Building (Scotland) Act 2003, and Northern Ireland has its own building regulations. GOV.UK points to separate guidance for both.
How does Estimark help with building control?
Estimark’s Building Control Pack bolt-on sits on the job in the web app. It assembles what a building control body reviews for an extension, a loft conversion, a change of use or a new build, on the full plans, building notice or regularisation route: the particulars read off the job, and every drawing at its current revision. Its notifiable works schedule lists electrics, gas, windows and doors, and heating as unrecorded until you confirm each route with the installer.
When you mark the pack sent, it records the date and keeps the exact PDF that went, and a sent pack stops the job being deleted, because the certificate gets asked for years later. It approves and certifies nothing, and you send it to the building control body yourself.
Sources
- The Building Regulations 2010, regulation 12 (legislation.gov.uk)
- The Building Regulations 2010, regulation 16 (legislation.gov.uk)
- The Building Regulations 2010, regulation 17 (legislation.gov.uk)
- The Building Regulations 2010, regulation 18 (legislation.gov.uk)
- The Building Regulations 2010, regulation 20 (legislation.gov.uk)
- The Building Regulations 2010, regulation 11C (legislation.gov.uk)
- The Building Regulations 2010, regulation 11T (legislation.gov.uk)
- The Building Regulations 2010, regulation 46A (legislation.gov.uk)
- The Building (Registered Building Control Approvers etc.) (England) Regulations 2024, regulation 13 (legislation.gov.uk)
- The Building (Registered Building Control Approvers etc.) (England) Regulations 2024, regulation 15 (legislation.gov.uk)
- The Building (Registered Building Control Approvers etc.) (England) Regulations 2024, regulation 18 (legislation.gov.uk)
- Building Act 1984, section 32 (legislation.gov.uk)
- Building Act 1984, section 35 (legislation.gov.uk)
- Building Act 1984, section 36 (legislation.gov.uk)
- Building Act 1984, section 51 (legislation.gov.uk)
- The Building etc. (Amendment) (No. 2) (Wales) Regulations 2025 (legislation.gov.uk)
- Building (Scotland) Act 2003, section 9 (legislation.gov.uk)
- Building regulations approval (GOV.UK)
Questions
Frequently asked
How long does a building control completion certificate take?
In England the local authority must give it within eight weeks of receiving the completion notice, where it is satisfied the work complies (regulation 17(2)). GOV.UK says to expect it within 8 weeks of completion on the full plans route.
Who applies for the completion certificate, the builder or the homeowner?
Nobody applies for it as such. The person carrying out the work gives the completion notice within five days of finishing, with signed statements from the client and the dutyholders, and the authority then gives the certificate if satisfied.
Is an approver’s final certificate the same as a completion certificate?
It does the same job by a different route. A registered building control approver gives the final certificate to the local authority under section 51 of the Building Act 1984, the council can reject it within ten working days, and it is evidence but not conclusive evidence of compliance.
Does a competent person scheme certificate replace a completion certificate?
For the work it covers, yes. A registered installer self-certifies and notifies building control within 30 days of finishing (regulation 20(3)), and GOV.UK says the certificate reaches you within 8 weeks of completion, so no separate building control application is needed for that work.
Can you get a completion certificate for work done years ago without approval?
Not a completion certificate, but the owner can apply to the local authority for a regularisation certificate under regulation 18, for work carried out on or after 11 November 1985. The authority may ask for the work to be opened up and tested first.
Is a completion certificate proof that the work complies?
It is evidence, but not conclusive evidence, that the requirements it names have been met. The regulations require the certificate to say so.
Read next
How to price a house extension
Scope first, the regulatory costs that get missed, the build-up in order, and the exclusions to write down.
What is practical completion, and who decides it?
No statutory definition, and retention, damages, insurance and the defects clock all change when it is certified.
Do you need planning permission for an extension?
Permitted development limits for rear and side extensions, prior approval, and where the rights do not apply.
Estimark: Building Control Pack
The documents a building control body reviews, assembled from the job. It approves nothing.
UK construction glossary
The contractual, tax and safety vocabulary, defined in a sentence each.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee and no card needed.