Programme
How to build a construction programme for a small job
The short answer
A construction programme is the plan of a job in time: each activity, how long it takes in working days, and which activities must finish before others can start. Link the activities, work forward from day one to find each activity’s earliest start and finish, then work back from the finish to find the latest. Activities with no spare time between the two form the critical path, and a delay to any of them delays completion. The spare time on the others is float. Save the first agreed version as the baseline, record progress against it at least monthly, and never overwrite a version: an as-planned programme set beside an as-built record is how a delay is proved.
At a glance
- Durations
- Working days, not calendar days
- Critical path
- The longest chain of linked activities
- Total float
- Delay an activity can take before completion moves
- Free float
- Delay an activity can take before the next one moves
- Updates (SCL Protocol)
- At intervals of no longer than one month
- England: notice before starting
- At least two days (Building Regulations 2010, reg. 16(1))
- England: commencement notice
- Within five days of commencement (reg. 16(3C))
- Spring 2027 bank holidays
- 26 and 29 March, 3 May (England and Wales)
What goes into a construction programme?
- Activities. Pieces of work one gang or trade can carry out and finish, such as ‘excavate foundations’ or ‘first fix electrics’. On a small job, 15 to 30 activities is enough.
- Durations. How long each activity takes, in working days, from your own outputs for the gang size you will put on it.
- Logic links. Which activity has to happen before which, and how they overlap.
- Milestones. Zero-length points that matter, such as start on site, weathertight, or the completion date in the contract.
- A calendar. The days you work, with weekends and bank holidays taken out.
The usual way of drawing it is a Gantt chart, a bar chart with one row per activity and time running left to right. The bars are only the picture. What makes it a programme you can manage and argue from is the logic behind them, because that is what moves the later bars when an early one slips.
Durations also drive cost. Site set-up, welfare, scaffold hire and supervision are time-related preliminaries, so the programme is where those prices come from, and a job priced from one programme and run to a longer one loses money every week it overruns.
How do logic links and lags work?
| Link | Means | Example |
|---|---|---|
| Finish to start | B cannot start until A has finished | The slab cannot be poured until the drainage under it is in |
| Start to start | B cannot start until A has started | Tiling can start in the kitchen once plastering has started elsewhere |
| Finish to finish | B cannot finish until A has finished | The final clean cannot finish until decorating has finished |
| Lag | A gap of a set number of days on a link | Second fix starts three days after plastering finishes, to let it dry |
Link definitions follow Appendix A of the SCL Delay and Disruption Protocol. The examples are illustrative.
Most links on a small job are finish to start. Use start to start and finish to finish where trades really do overlap, and use a lag for a wait that needs no labour, such as curing or drying. Do not use a lag to hide work: a lag of ten days for ‘steel delivery’ should be an activity with its own duration, so it shows up when it is late.
What is the critical path, and how do you find it?
The critical path is the longest sequence of activities through a project network from start to finish, the sum of whose durations determines the overall project duration. (SCL Delay and Disruption Protocol, Appendix A)
Forward pass: the earliest dates
Start the first activity on day 1. Its early finish is its start plus its duration, less one, because work starts at the beginning of the first day and finishes at the end of the last. Each following activity starts the day after the latest early finish of everything it depends on, plus any lag. Carry on to the last activity. Its early finish is the shortest possible length of the job.
Backward pass: the latest dates
Now start at the end. The last activity’s late finish is the job’s finish day. Each earlier activity must finish by the day before the earliest late start among the activities that follow it, less any lag. Its late start is its late finish less its duration, plus one.
Float: the spare time
Total float is late start minus early start: how long an activity can slip before completion moves. Free float is how long it can slip before the next activity’s early start moves. Activities with zero total float are the critical path. Free float matters when two trades are booked back to back: using an activity’s total float may be harmless to completion and still leave the next trade standing.
Free toolUK construction glossaryCritical path, float, extension of time, liquidated damages and the rest of the contract vocabulary, defined in a sentence each.What does a programme for a single-storey extension look like?
A rear extension with a steel over the opening into the house, built by a small firm with its own bricklayers and subcontracted trades. Durations are working days. The steel and the windows are entered as activities with their own make-and-deliver time, ordered on day 1.
| No. | Activity | Days | Follows | Early start | Early finish | Total float |
|---|---|---|---|---|---|---|
| 1 | Set up site, welfare, set out | 2 | None | 1 | 2 | 0, critical |
| 2 | Excavate foundations | 2 | 1 | 3 | 4 | 0, critical |
| 3 | Concrete foundations | 1 | 2 | 5 | 5 | 0, critical |
| 4 | Brick and block to DPC | 3 | 3 | 6 | 8 | 0, critical |
| 5 | Below-ground drainage | 3 | 2 | 5 | 7 | 1 |
| 6 | Ground floor slab | 2 | 4, 5 | 9 | 10 | 0, critical |
| 7 | External walls to wall plate | 8 | 6 | 11 | 18 | 0, critical |
| 8 | Steel made and delivered | 15 | None | 1 | 15 | 3 |
| 9 | Form opening, fit steel | 2 | 7, 8 | 19 | 20 | 0, critical |
| 10 | Roof structure and covering | 6 | 9 | 21 | 26 | 0, critical |
| 11 | Windows and doors made and delivered | 25 | None | 1 | 25 | 1 |
| 12 | Fit windows and doors | 2 | 10, 11 | 27 | 28 | 0, critical |
| 13 | First fix electrics and plumbing | 4 | 12 | 29 | 32 | 0, critical |
| 14 | Plaster | 4 | 13 | 33 | 36 | 0, critical |
| 15 | Second fix | 4 | 14, plus 3-day lag | 40 | 43 | 0, critical |
| 16 | Decorate | 3 | 15 | 44 | 46 | 0, critical |
| 17 | External drainage connections | 2 | 10 | 27 | 28 | 15 |
| 18 | Paths and making good outside | 3 | 17 | 29 | 31 | 15 |
| 19 | Snag, clean, completion | 2 | 16, 18 | 47 | 48 | 0, critical |
Illustrative programme for a worked example. Durations and lead times are invented, not market figures.
The forward pass gives 48 working days. The critical path runs 1, 2, 3, 4, 6, 7, 9, 10, 12, 13, 14, 15, 16, 19: two days, two, one, three, two, eight, two, six, two, four, four, the three-day lag, four, three and two, which add up to 48. Every one of those has zero total float.
The near misses are where the risk sits. The windows have one day of float: if they arrive two days late, the job finishes a day late. The steel has three. Activity 17 has 15 days of total float but no free float, because any slip in it pushes activity 18 straight back. Completion only moves once the two together slip by more than 15 days.
Start it on Monday 1 March 2027 and day 48 is not Wednesday 5 May, as a count of weekdays would suggest. Good Friday (26 March), Easter Monday (29 March) and the early May bank holiday (3 May) all fall inside it, so day 48 is Monday 10 May. Pricing the same job? The extension pricing guide works through the cost side.
How do you allow for lead times, bank holidays and weather?
- Long-lead items as activities. Steels, windows, roof lights, bespoke doors and anything made to measure get their own row, starting from the date you can order and lasting until delivery. Confirm the lead time with the supplier when you order, then put it in the programme rather than in your head.
- Order dates as milestones. Some items cannot be ordered until something else happens, such as the engineer’s calculation or a site measure. Link the order to that event, so a late drawing shows up as a late window.
- A working-day calendar. Take out weekends and bank holidays. In England and Wales the remaining 2026 dates are 25 December and 28 December, the substitute for Boxing Day. In 2027 they are 1 January, 26 March, 29 March, 3 May, 31 May, 30 August, and 27 and 28 December, both substitute days. Scotland and Northern Ireland have different dates.
- Weather. Put the weather you would expect for the season into the durations of weather-sensitive work: groundworks, external brickwork, roofing and concrete. Where a contract gives time for adverse weather, it may give no money with it: the SCL Protocol names adverse weather as the most common example of an event that carries time but no compensation for prolongation. Read your contract to see what it allows.
NoteCheck the GOV.UK bank holidays page when you set up a programme that runs into a new year. Dates are added and occasionally changed, and an extra holiday moves every later activity by a day.
Which building control stages should the programme allow for?
Where building work in England is under the building notice or full plans route, regulation 16 of the Building Regulations 2010 sets the notices. Build them into the programme as milestones, because the clock starts from them.
- 01Before you start. Notice of intention to start work, and at least two days must have passed since the end of the day it was given (regulation 16(1)).
- 02Stages the authority asks for. The authority may serve a notice requiring you to tell it when a specified stage is reached, and may set when that notification must be made and a period during which the work must not be covered up. It can only do so where it intends to inspect that stage (regulation 16(3) to (3B)). Put every stage it names on the programme, with the wait.
- 03Commencement. Not more than five days after the work is regarded as commenced, a commencement notice (regulation 16(3C)). For a horizontal extension, regulation 46A treats the work as commenced when the sub-surface structure, including all foundations and the structure of the ground floor, is completed. In the example, that is the end of activity 6.
- 04Completion. Not more than five days after completion, a completion notice with the statements regulation 16(4A) lists (regulation 16(4)).
NoteWales has its own version of regulation 16. Alongside the same two-day notice before starting and five-day completion notice, it still requires notice before covering up foundation excavations, foundations, the damp-proof course, oversite concrete and drains, with at least one day elapsed, and notice within five days after laying, haunching or covering a drain or sewer. Since 1 July 2026 it also requires a commencement notice within five days of the work being regarded as commenced. A registered building control approver works under separate regulations, so agree its notification stages at the start.
Why keep a baseline, and how do you update the programme?
The baseline is the programme as first agreed, saved and left alone. Every later version is measured against it. Without it, there is nothing to show what the plan was before the delay happened.
- 01Save the baseline when the client or contract administrator accepts it, or on the day you start if nobody asks for one.
- 02Update regularly. Record actual start and finish dates, the percentage complete of activities in progress and the remaining durations. The SCL Protocol recommends updates at intervals of no longer than one month; weekly suits a short job.
- 03Save each update as a new version. The Protocol says no version of any programme should be overwritten. The run of updates becomes the as-built record: what actually happened, activity by activity.
- 04Look three weeks ahead. Each week, take the next three weeks of the updated programme and break it down into the trades, deliveries and inspections to book. The Protocol counts short-term look-ahead programmes among its programme records.
- 05Check it against the diary. Actual dates should match the site diary. If the diary says the roof was finished on the 14th, the programme should too.
How does the programme prove an extension of time?
An extension of time needs a delay that hit the critical path. The baseline shows the as-planned sequence and the float each activity had; the updates and the diary show the as-built dates. Set one beside the other and the delay to each activity can be measured, with a cause and a date against it.
Float decides how much of a delay counts. The SCL Protocol’s Core Principle 8 says that, unless the contract provides otherwise, where total float remains when an employer risk event happens, an extension should only be granted to the extent the delay is predicted to reduce total float on the critical path below zero. In the example, if a late client decision made the windows four days late, the first day would use up their one day of float and completion would move by three.
Where an extension is refused, liquidated damages run from the original date, and the programme is your evidence against them.
How does Estimark help you plan and run the work?
Estimark shows every live job by stage on a board, from pending through active, on hold, complete and invoiced, and the same jobs as a list, a calendar or a table. Labour is planned a week at a time on a resource schedule, with jobs nobody is on yet in an unassigned strip ready to drag onto a person and a day. Extra work is raised as a variation with a number, a price and an approval stage. The site diary keeps delays in their own field, so the record behind an as-built programme can be pulled out as a set. See jobs and scheduling in Estimark.
Sources
Questions
Frequently asked
What is the critical path in construction?
The longest chain of linked activities from start to finish. Its total duration is the length of the job, and a delay to any activity on it delays completion unless the work is accelerated or resequenced.
How does total float differ from free float?
Total float is how long an activity can slip before the completion date moves. Free float is how long it can slip before the next activity’s earliest start moves. An activity can have plenty of total float and no free float at all.
How often should a programme be updated?
The SCL Delay and Disruption Protocol recommends intervals of no longer than one month. On a short job, a weekly update alongside a three-week look-ahead is more useful. Save each update as a new version.
Do I need programming software for a small job?
Not to start. A spreadsheet or a hand-drawn bar chart works for 20 activities if you write down the links and do the forward and backward pass. Software earns its place when the logic changes often, because it recalculates the float for you.
Who owns the float in a programme?
It depends on the contract. Where the contract says nothing, the SCL Protocol’s position is that an extension of time should only be granted to the extent an employer delay reduces total float on the critical path below zero.
Should I count bank holidays as working days?
No. Use a calendar with weekends and bank holidays removed, and check the GOV.UK list for the years the job runs into. Three bank holidays fall between late March and early May in 2027.
Read next
How to keep a site diary that holds up in a dispute
What to record each day, who should write it, and why a diary written on the day beats memory.
Extension of time: what you must prove and by when
The relevant event, the critical delay, the notice deadline and the records behind all three.
What are preliminaries, and how do you price them?
Why most prelims run by the week, and how a longer programme turns into a loss.
How to price a house extension
Scope first, the regulatory costs that get missed, the build-up in order, and the exclusions to write down.
Estimark: jobs and scheduling
Every live job by stage, a weekly resource schedule, and variations numbered, priced and approved.
UK construction glossary
The contractual, tax and safety vocabulary, defined in a sentence each.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee and no card needed.