Health and safety
Do small building jobs need a RAMS?
The short answer
No law requires a document called a RAMS, but every job needs a suitable and sufficient risk assessment under regulation 3 of the Management of Health and Safety at Work Regulations 1999, and every construction project, a domestic one included, needs a construction phase plan before the site is set up under CDM 2015. If you employ five or more people, the significant findings of the risk assessment must be written down. HSE says method statements are not required by law, but demolition, dismantling and structural alteration must have their arrangements recorded in writing before the work starts. On a small job a short, specific risk assessment and plan, briefed to the people doing the work, meets the duty. A main contractor can still make a written RAMS a condition of letting you on site.
At a glance
- Risk assessment
- Every job, under MHSWR 1999 regulation 3
- Written down when
- Five or more employees
- Construction phase plan
- Every project, before the site is set up
- Domestic client
- Client duties pass to the contractor
- Method statement
- Not required by law in itself
- Must be in writing first
- Demolition, dismantling, structural alteration
What does the law actually require on a small job?
Three duties apply whatever the size of the job, and none of them uses the word RAMS.
- 01A risk assessment. Regulation 3(1) of the Management of Health and Safety at Work Regulations 1999 requires every employer to make a suitable and sufficient assessment of the risks to its employees and to anybody else affected by the work, such as the homeowner and the neighbours.
- 02A construction phase plan. Under CDM 2015 the only contractor on a project draws up a construction phase plan, or arranges for one, as early as practicable before setting up the site (regulation 15(5)). Where there is more than one contractor, the principal contractor does it (regulation 12(1)).
- 03Information, instruction and an induction. Regulation 15(8) requires each contractor to give its workers the supervision, instructions and information they need to work safely, and 15(9)(a) adds a site induction where the principal contractor has not already given one.
HSE: method statements are not required by law, but they are prepared for many construction activities. Arrangements for demolition, dismantling or structural alteration must be recorded in writing before the work begins.
Does the five-employee rule mean I can skip writing it down?
Only the writing. Regulation 3(6) says an employer with five or more employees must record the significant findings of the assessment and any group of employees identified as especially at risk. Below five, the assessment still has to be made and acted on, and it still has to be suitable and sufficient. It just does not have to be on paper.
In practice a small firm writes it down anyway, for three reasons. The construction phase plan is a written document in its own right. A main contractor or a commercial client will ask for the assessment before you start. And if somebody is hurt, a record dated before the work began is the only way to show what you assessed and what you told the team.
What changes when the customer is a homeowner?
CDM 2015 applies to domestic work too. What changes is who carries the client’s duties. Under regulation 7(1), a domestic client’s duties fall to the contractor where there is only one, or to the principal contractor where there are several, unless the homeowner agrees in writing that the principal designer will take them on.
So on a kitchen extension where you are the only contractor, you hold the client’s duties as well as your own: you make sure the arrangements for managing the project are suitable, that welfare is provided, and that the plan exists before the site is set up. If you bring in an electrician and a plasterer as separate contractors, there is more than one contractor and regulation 5(1) requires a principal designer and a principal contractor to be appointed.
Whether the job also has to be notified to HSE on an F10 is a separate test of duration and person-days, covered in CDM 2015 and the F10.
How short can a RAMS for a small job be?
As short as the job allows, provided it is about this job. A page that names the address, the task, the hazards on that site and the controls for each, and the people briefed on it, meets the duty better than twenty pages of generic text nobody reads. For a two-day bathroom strip-out it might cover:
- The address, the client, the dates and who is in charge on site.
- The task in a few sentences, in the order it will be done.
- The hazards that apply here: silica dust from cutting tiles, asbestos in an older property until a survey says otherwise, manual handling of the old bath, work near live services, and the occupants still living in the house.
- The control for each, in plain words: on-tool extraction and the right mask, isolation before the electrics are touched, two people for the bath, the working area kept closed to the family.
- First aid, the nearest A&E, and where the welfare facilities are.
- The names and signatures of everybody briefed, with the date.
The full list of what a fuller RAMS carries, and why principal contractors send them back, is in what must a RAMS contain.
When does a small job need more than a short assessment?
- Removing a wall or any structural alteration. HSE expects the arrangements in writing before the work begins, including the temporary support.
- Work at height beyond a stepladder for a short task. The planning duty and the hierarchy are in work at height: the rules for builders.
- Hot works, where a permit is the usual control. See when do you need a hot works permit.
- Anything that disturbs a pre-2000 building’s fabric, where asbestos has to be considered before the work, not during it.
- A change on the day. Regulation 3(3) requires the assessment to be reviewed when there is reason to think it is no longer valid or there has been a significant change. A wall that turns out to be load-bearing is one.
Why do main contractors ask for a RAMS on every job?
Because their own duties depend on yours. A principal contractor has to plan, manage and coordinate the construction phase, and the subcontractor’s risk assessment and method of work are the evidence that it did. Asking for a RAMS is how it collects that evidence before you arrive. The request is contractual, not statutory, but without one you do not start.
A RAMS that names the right site, the right task and the people who will actually do it is accepted first time far more often than a generic one. Keeping your own versions per job, rather than editing last month’s Word file, is what stops the wrong address going out.
How does Estimark handle RAMS?
In Estimark a RAMS belongs to the job. You write it on the web from a template or have a first draft written from a description of the work or an uploaded file, then check it, issue it and print it as a PDF. Change the method and you issue a new version, with the old one kept. On site, the person in charge takes each operative’s drawn signature against the issued version on the iPhone or the Android app, so the record of who was briefed sits next to the document they were briefed on. Inductions, toolbox talks, permits to work and near-miss reports are in the same Health & Safety module, included from Solo.
NoteEstimark does not write your construction phase plan, and a drafted RAMS is a starting point for a competent person to check against the site, not a finished assessment.
Sources
- Management of Health and Safety at Work Regulations 1999, regulation 3 (legislation.gov.uk)
- Construction: what you need to do (HSE)
- CDM 2015, regulation 5 (legislation.gov.uk)
- CDM 2015, regulation 7 (legislation.gov.uk)
- CDM 2015, regulation 12 (legislation.gov.uk)
- CDM 2015, regulation 15 (legislation.gov.uk)
Questions
Frequently asked
Is a RAMS a legal requirement?
Not by that name. A risk assessment is required on every job under regulation 3 of the Management of Health and Safety at Work Regulations 1999, and a construction phase plan on every project under CDM 2015. HSE says a method statement is not required by law, except that demolition, dismantling and structural alteration must have their arrangements written down before work starts.
Do I need a written risk assessment if I work alone?
The duty to record significant findings applies to employers with five or more employees. A sole trader still has to assess the risks to other people affected by the work and still needs a construction phase plan for the project, which is a written document.
Does CDM 2015 apply to work in someone’s home?
Yes. The homeowner is a domestic client, and under regulation 7 their client duties pass to the contractor if there is only one, or to the principal contractor if there are several.
How long should a RAMS for a small job be?
No law sets a length. It has to be suitable and sufficient for the job, which on a small job can be a page or two, provided it names the site, the task, the hazards there and the controls, and the people briefed.
Can I reuse the same RAMS on every job?
You can start from the same template, but the assessment has to fit the site. Regulation 3(3) requires a review when the assessment is no longer valid or something significant changes, and a different house is a different set of hazards.
Read next
What must a RAMS actually contain?
The legal duty behind it, the sections a good one has, and what gets them rejected.
CDM 2015: when do I notify HSE on an F10?
The two thresholds, who notifies, and the duties that apply whether you notify or not.
What should a site induction cover?
The CDM 2015 duty, what an induction must cover on the day, and the record that proves it happened.
RAMS template
Risk assessment, method statement, emergency arrangements and a signed briefing record.
Estimark: RAMS & site safety
Versioned RAMS, operative sign-off, inductions and a live muster roll.
Estimark pricing
Solo £39 +VAT, Core £129 +VAT and Pro £299 +VAT a month plus seats, Enterprise quoted. 14-day free trial.
RAMS software
Risk assessments and method statements built once, issued per job and signed on site.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee and no card needed.