Provisional sum

An allowance in a contract sum for work not yet defined well enough to price, to be expended as instructed and adjusted against actual cost. A defined provisional sum is one the contractor has enough information to have allowed for in their programme; an undefined one is not, and an undefined sum expended can carry an extension of time with it.