What is cost value reconciliation (CVR), and how do you run one?

10 min read

The short answer

Cost value reconciliation (CVR) is a monthly profit and loss statement for each job. At one cut-off date you compare the value of the work done, from your own internal valuation rather than the last certificate, with the full cost of doing it, including costs incurred but not yet invoiced. Value less cost is your margin to date. Then you look forward: cost to date plus the cost to complete, including orders already placed, gives the forecast final cost, and the forecast final value less that figure gives the forecast final margin. RICS practice information describes the CVR as the project’s profit and loss statement, comparing the internal valuation with the costs incurred, accruals included. Run it every month on every live job and a losing job shows itself while there is still time to act.

At a glance

Compares
Value of work done with the cost of doing it
Cut-off
The same date for cost and value
Frequency
Monthly, usually at the accounting period end
Margin to date
Internal value less cost to date
Forecast final cost
Cost to date plus cost to complete
Forecast margin
Forecast final value less forecast final cost
RICS reference
Commercial management of construction, 1st edition
FRS 102 Section 23
New revenue model for periods from 1 January 2026

What is a CVR, in plain terms?

A CVR answers one question per job: on the last day of the month, how much have we earned, how much has it cost us, and what will it look like when it finishes? It sets value against cost at the same date, and then forecasts both to the end of the job.

It is not the bank balance and it is not the annual accounts. The bank balance tells you about cash, which lags both value and cost. The accounts arrive months after the year end, too late to change anything on a job that has already finished. The CVR is the monthly view in between, job by job.

A CVR compares like with like: value and cost cut off at the same date, analysed under the same headings the job was priced under.

NoteA CVR is a management tool. Statutory accounts follow FRS 102, whose Section 23 became ‘Revenue from Contracts with Customers’, a five-step model, for accounting periods beginning on or after 1 January 2026. Your accountant decides how CVR figures feed into the accounts.

What counts as value in a CVR?

Value is what the work done to the cut-off date is worth under the contract. Several figures compete for the title, and only one of them belongs in the CVR.

  • Applied value. What you asked for in your last application for payment. Your opening bid, not your value.
  • Certified value. What the client or their quantity surveyor certified. Firmer, but cut off at the valuation date, which is rarely your month end.
  • Internal valuation. Your own honest assessment of the work actually done at the cut-off date. This is the value in a CVR.
  • Unagreed variations. Instructed work not yet valued by the client. Include it at a prudent figure, under a policy you write down and apply every month. See variations: how to record and price them.
  • Work done since the last valuation. The internal valuation picks up work between the valuation date and the cut-off. This is the value accrual.
  • Over and under valuation. The gap between what was certified and what your internal valuation says the work is worth. Over-valuation flatters the month and gets taken back later; under-valuation hides margin and costs you cash.

RICS calls that last gap over or under measure, and notes that accountants tend to call it positive or negative work in progress. Either way, track it every month, because it shows where the valuation is ahead of or behind the work.

What counts as cost, and how should it be coded?

  • Actual cost. Invoices posted, wages paid, plant hire charged, all booked to the job.
  • Accrued cost. Goods and services received by the cut-off but not yet invoiced: delivery notes with no invoice, subcontract work done since their last application, the last week of hours not yet through payroll. Leave these out and the job looks better than it is.
  • Committed cost. Orders placed through purchase orders and subcontract orders but not yet delivered or done. Not cost to date, but it is cost already spoken for, and it is the first part of the cost to complete.
  • Cost to complete. The forecast cost of everything left to do: labour days at current rates, plant hire days, materials still to buy, the rest of each subcontract package and anything not yet ordered.

Hours booked to the right job are the labour line of the CVR, so the timesheet is a commercial record as much as a payroll one: see construction timesheets.

Cost codes

A cost code is the heading a cost is booked under. Use the same headings the job was priced under: labour, materials, plant, subcontract and preliminaries at least, and by stage or element on bigger jobs. RICS stresses that costs have to be collated at the same levels as the values, or the comparison line by line cannot be made. A cost booked to the wrong job, or to ‘general’, is a cost the CVR cannot see.

How do you forecast the final cost and margin?

FigureHow it is worked out
Cost to dateActual cost plus accruals, less recoveries, plus provisions
Cost to completeCommitted cost plus everything still to buy, hire, employ or subcontract
Forecast final costCost to date plus cost to complete
Forecast final valueContract sum plus agreed variations, plus a prudent figure for unagreed ones
Forecast final marginForecast final value less forecast final cost

The cost to complete is a judgement, made element by element by somebody who knows the job. Forecasting it as ‘whatever is left in the budget’ assumes the job finishes exactly on budget, which is the one thing a CVR is supposed to test.

How do you run a CVR each month?

  1. 01Fix the cut-off date. The same date for cost and value, normally the month end. RICS suggests a monthly commercial calendar so everyone works to the same timetable.
  2. 02Value the work. Start from the latest certificate and adjust to your internal valuation at the cut-off.
  3. 03Deal with variations. Agreed ones in full, unagreed ones at your prudent figure, with the basis written down.
  4. 04Collect the cost. Everything posted to the job, then accruals for goods, subcontract work and hours received but not yet invoiced or paid. Move anything booked to the wrong job.
  5. 05Make the adjustments. Contra charges recoverable, provisions for known defects, claims against you.
  6. 06Compare. Value less cost gives margin to date. Then check the movement since last month: an unexplained swing in either is usually an error.
  7. 07Go line by line. Compare each cost code and each element against the budget, and find which heading the variance sits in.
  8. 08Forecast. Cost to complete by element, then forecast final cost and forecast final margin.
  9. 09Record and explain. What changed, why, who signed it off and what you will do about it. Keep a lessons log so the next estimate benefits.

Which adjustments make or break a CVR?

  • Preliminaries. Time-related prelims are spent by the week. If the job is running late, they are costing more than the value recovered for them, and the CVR should say so. See preliminaries and how to price them.
  • Retention. Retention reduces cash, not value. Keep value gross and track retention separately, and only provide against it where you have a real reason to think it will not come back. See retention and getting it released.
  • Contra charges. A charge you will deduct from a subcontractor for their damage or failure reduces your cost, but only once it is properly notified and you are confident of recovering it. A contra charge against you is cost.
  • Defects provisions. Remedial work you know about but have not done is a cost now, even though you will incur it later.
  • Claims not yet agreed. Loss and expense, extensions of time, disputed variations. Take them into value cautiously, under a documented policy, or not at all. RICS counsels prudence: over-valuing change helps nobody, and under-valuing it is not advised either.

Value taken on hope comes back out later, usually in the last month of the job, when nothing can be done about it.

Can you show me a worked example?

A refurbishment with a contract sum of £240,000 and £12,000 of approved variations, priced at an 18% margin, at the end of month 5 of 8.

LineAmount
Value certified at the last valuation (gross)£118,000
Add work done between the valuation and the cut-off£9,000
Add unagreed variations at a prudent figure (£8,000 claimed)£3,000
Less over-valuation of preliminaries in the certificate−£4,000
Internal value to date£126,000
Cost posted to the job£92,000
Add accruals: goods and subcontract work not yet invoiced£14,000
Add provision for known remedial work£1,500
Less contra charge recoverable from the groundworker−£1,200
Cost to date£106,300
Margin to date£19,700 (15.6% of value)
Cost to complete, including £21,000 committed on orders£108,000
Forecast final cost£214,300
Forecast final value (£252,000 plus £3,000)£255,000
Forecast final margin£40,700 (16.0%)

Illustrative figures for a worked example, not market rates or typical margins.

Read it against the shortcut. Certified value less cost posted is £26,000, which looks like 22%. Once the work done since the valuation, the prudent variation figure, the over-valued prelims, the accruals, the provision and the contra charge are in, the job is making 15.6% to date and is forecast to finish at 16.0%, two points below the 18% it was priced at.

Free toolMarkup vs margin calculatorCheck what the tender margin really was as a markup on cost, and the price a target margin needs.

What are the warning signs in a CVR?

  • Margin slipping month after month. One bad month can be timing. Three in a row is a trend, and the same slide on job after job means the estimating is wrong.
  • Value running ahead of cost. A job showing a far better margin than it was priced at, early on, is usually over-valued or missing accruals.
  • Under-recovered prelims. The programme has slipped and the weekly costs are running past what the valuation pays for them.
  • A cost to complete that never moves. If it is the budget less cost to date every month, nobody is forecasting.
  • Growing unagreed variations. A rising share of value that the client has not accepted is margin you may not get.
  • Accruals growing faster than the work. Costs are arriving that nobody has matched to an order.

How does Estimark support a CVR?

Estimark builds a live cost position for each job from three feeds: timesheet hours at the rate held on them, purchase orders as they are receipted, and cost ledger entries you post. Cost is split six ways, into labour, materials, plant, subcontractor, preliminaries and other, against your own cost codes. Committed cost is the VAT-exclusive value of purchase orders issued but not yet received, and it moves into actual cost as goods are receipted.

Budgets are frozen as versioned baselines, and a cost to complete is entered per period end with the name of whoever made the call. Where nobody has entered one, the forecast is derived from committed cost and the unspent budget, and the position says so. The CVR carries contract value, approved variations, revised contract value, value certified from payment applications, actual and committed cost, cost to complete, forecast final cost, variance and margin, per job and as a portfolio pack, and exports to CSV. See job costing and CVR and the job costing module.

Sources

Questions

Frequently asked

How often should a small contractor run a CVR?

Monthly, on every live job, with the same cut-off date for cost and value. A job of a few weeks still needs one at the end of each month it spans and one at completion.

Is a CVR the same as a WIP report?

No. RICS describes the gap between your external valuation and your internal valuation as over or under measure, which accountants tend to call positive or negative work in progress. The CVR uses that gap as one input; it then sets the whole of value against the whole of cost.

Should unagreed variations go into the value?

At a prudent figure, under a written policy applied the same way every month. Taking them at the full amount claimed flatters the margin until the client values them, then takes it back in one go.

Does retention reduce the value in a CVR?

No. Retention is part of the value you have earned; it is held back as cash. Keep value gross, track retention separately and provide against it only when there is a specific reason to doubt it will be released.

What margin should a CVR show?

The margin you priced the job at, adjusted for what has changed since. There is no industry standard figure to compare against. The useful comparison is your own: the tender margin, last month’s forecast, and the same type of job last year.

Do I need an accountant to run a CVR?

No. It is a commercial exercise run by whoever knows the job and the costs. Your accountant uses its figures when preparing the statutory accounts, which follow FRS 102.