Estimating

How to price a bathroom refit

12 min read

The short answer

Price a bathroom refit in the order the work happens: strip-out and waste, first fix plumbing and electrics, boarding and waterproofing, tiling, second fix, then decoration and making good. Survey what is behind the old suite before you fix a figure: the floor, the waste route, the water pressure, and in a house built before 2000 the chance of asbestos. In England, a new circuit, or any addition or alteration to circuits in the space around the bath or shower, is notifiable electrical work. Approved Document F sets a bathroom extract rate of 15 litres per second for an intermittent fan. Replacing a bath, toilet or basin needs no Building Regulations approval. Price the tiles and the suite as allowances if the client has not chosen them. A refit is standard-rated for VAT, but work to suit a disabled person’s condition can be zero-rated.

At a glance

Before strip-out
Assess for asbestos (CAR 2012, reg 5)
Notifiable electrics (England)
New circuit, or work in the bath or shower zone
Intermittent extract
15 litres per second
Continuous extract
8 litres per second at the high rate
Bath over 230 litres
Water company consent first (England and Wales)
Replacing bath, WC or basin
No Building Regulations approval needed
VAT
20%, or zero for qualifying work for a disabled person

What makes a bathroom refit different to price?

It is one small room with five trades in it, often the only bathroom in the house, and most of what decides the cost is hidden behind tiles and under the floor until the old suite comes out. The general method of building up a price is in how to price a house extension. For a bathroom, the survey does most of the work.

  • The floor. Lift a board if you can. Look for notched joists, rot around the toilet and under the bath, and whether the floor is flat enough for tiles.
  • The waste route. Where the soil pipe and wastes run, the fall available, and whether a new layout moves the toilet away from the stack.
  • Water supply and hot water. The hot water system and the pressure and flow at the tap decide which shower will work, and whether a pump is needed.
  • The fan. Is there one, does it work, and where does it vent?
  • The electrics. What is in the room, and whether the client wants an electric shower, a heated towel rail or underfloor heating, each of which can mean a new circuit.
  • Access. Getting a bath up the stairs, and somewhere for the waste.
  • Who supplies what. If the client is buying the suite or the tiles, the price changes and so does who carries the delivery risk.

Price what you saw, carry a provisional sum for what you could not, and say in the quote which is which.

What does the strip-out involve, and what about asbestos?

Strip-out is the suite, the tiles, often the wall boards and sometimes the ceiling, and every piece of it leaves the house through the client’s hall. Price the labour, the protection and the waste separately: a cast iron bath and a wall of tiles on render fill a skip faster than they look. See construction waste: your duty of care.

In an older house, find out about asbestos before anything comes off the wall. Regulation 5 of the Control of Asbestos Regulations 2012 says an employer must not start work that could expose employees to asbestos unless it has assessed whether asbestos is present, or, where there is doubt, assumes it is and follows the Regulations. HSE says asbestos was used in buildings until it was banned in 1999, that buildings constructed after 2000 are unlikely to contain it, and that contractors working in a home have a legal duty to protect the people living there from the risks of their work.

Read which asbestos survey you need before pricing the strip-out of a pre-2000 bathroom, and put the survey and any removal in the quote or the exclusions.

How do you price the plumbing, and what do the water fittings rules say?

First fix is the pipe runs, the wastes and the concealed shower valve, set out to the positions on the client’s chosen suite. Second fix is fitting the suite and brassware, connecting and testing. Price first fix from the layout: a suite in the same positions is quick, a toilet moved across the room is a new soil run, and possibly a new floor.

In England and Wales, the Water Supply (Water Fittings) Regulations 1999 apply to every fitting that carries or receives water from a water company’s supply:

  • No waste or contamination. No fitting may be installed, connected, arranged or used so that it causes, or is likely to cause, waste, misuse, undue consumption or contamination of water (regulation 3).
  • The right fittings, fitted properly. Each fitting must be of an appropriate quality and standard, such as conforming to a British Standard or equivalent, and be installed in a workmanlike manner (regulation 4).
  • Notify before some work. Regulation 5 requires notice to the water company, and its consent, before installing a bath holding more than 230 litres to the centre line of the overflow, a bidet with an ascending spray or flexible hose, or a pump or booster drawing more than 12 litres a minute. The company has ten working days to refuse or set conditions, and if it says nothing, consent is deemed. A bidet fitted by an approved contractor needs no notice.

NoteA large freestanding bath or a pumped shower can trigger the notice. Build the ten working days into the programme, not the week the bath arrives.

GOV.UK lists replacing baths, toilets, basins and sinks as work that needs no Building Regulations approval, and installing a bathroom that will involve plumbing as work that might. A new bathroom where there was none, or new drainage, is a question for building control before you price it.

What electrical work in a bathroom has to be notified?

In England, regulation 12(6A) of the Building Regulations 2010 makes three kinds of electrical work notifiable: a new circuit, replacing a consumer unit, and any addition or alteration to existing circuits in a special location, which includes the space around a bath or shower. An electric shower on its own new circuit is notifiable. So is moving a light or a fan within the zone.

The work is either self-certified by an electrician registered with a competent person scheme, or notified to building control before it starts. Either way it is the electrician’s price and the electrician’s certificate, and you need to know which route before first fix. The zone dimensions, the routes and Wales’s wider rules are in Part P: which electrical work must be notified?

One saving: Approved Document F says an extractor fan replaced using the existing cabling does not need to be notified to building control.

What extract ventilation does a bathroom need?

Approved Document F volume 1 says extract ventilation to the outside should be provided in bathrooms, and sets these minimum rates:

SystemMinimum bathroom extract rate
Intermittent extract fan15 litres per second
Continuous extract, high rate8 litres per second

Approved Document F volume 1, 2021 edition, Tables 1.1 and 1.2 (England). The 2026 edition, in effect from 24 March 2027, keeps both figures.

Fans should be fitted as high as practicable and no more than 400 millimetres below the ceiling. What applies to your job depends on whether the bathroom is new or a refit.

  • Refitting an existing bathroom. Keep or replace any existing fan, and check that a retained one works. If the room had no ventilation system, Approved Document F says it is not necessary to provide one, unless the refurbishment is likely to make the house less compliant than before.
  • Adding a bathroom where there was none. Provide an intermittent fan at the Table 1.1 rate with a background ventilator of at least 5,000 square millimetres equivalent area, or continuous extract at the Table 1.2 rate, or a single-room heat recovery ventilator, and undercut the door so air can reach it: 10 millimetres above a fitted floor finish.

Even where no rule forces a new fan, a sealed, freshly tiled room with no extract is a mould complaint waiting to happen. Price one in, or write its omission into the exclusions.

In what order do the trades go, and where do waterproofing and tiling fit?

  1. 01Protection and strip-out, with the water isolated and the waste out of the house.
  2. 02Floor repairs, once you can see the joists.
  3. 03First fix plumbing and wastes, to the suite’s actual positions.
  4. 04First fix electrics and fan ducting.
  5. 05Boarding and waterproofing, with plastering where walls are not being tiled.
  6. 06Tiling, walls then floor.
  7. 07Second fix plumbing: the suite, the shower and the brassware.
  8. 08Second fix electrics, testing and the certificate.
  9. 09Sealing, decoration and making good, then the snag list with the client.

Waterproofing

This is where cheap bathrooms fail. Tank the wet areas, meaning the shower walls and floor and the wall above the bath, with one manufacturer’s system of board, membrane, tape and adhesive, fitted to its instructions. A leak through grout shows up in the ceiling below months later and can cost more to put right than the tiling did.

Tiling

Measure the areas and count the cuts, around the window, the bath and the boxing-in. Large format tiles need flatter walls and more care; small mosaics need more hours. Until the client has chosen, price the tiles as a prime cost sum per square metre and say so. See provisional sums and PC sums.

Each trade waits on the one before. A plumber who is a day late on first fix holds up the boards, the tiler and the second fix, so price the time the room is out of use, not only the hours on the tools.

What does a bathroom refit build-up look like?

A family bathroom refitted in the same layout: bath with a thermostatic shower over, new toilet and basin, replacement fan, walls tiled around the bath and floor tiled. Every figure is made up to show the method.

StageLabourMaterialsPlant and wasteSubcontractStage cost
Protection and strip-out£700£50£0£0£750
Waste removal£0£0£300£0£300
First fix plumbing£600£250£0£0£850
First fix electrics and fan£0£0£0£450£450
Boarding, waterproofing and plastering£700£450£0£350£1,500
Tiling, walls and floor£1,200£300£0£0£1,500
Tiles (prime cost sum)£0£900£0£0£900
Sanitaryware and brassware£0£1,800£0£0£1,800
Second fix plumbing£650£100£0£0£750
Second fix electrics, test and certificate£0£0£0£300£300
Decoration and making good£400£100£0£0£500
Direct cost£4,250£3,950£300£1,100£9,600

Illustrative figures for a worked example, not market rates. Price from your own rates and your subcontractors’ quotes.

Overhead, then margin. The firm’s own labour is 125 hours at a true cost of £34 an hour; £20 of overhead on each hour adds £2,500, making £12,100, and a 12% margin on the price gives £13,750 before VAT. The method behind those two steps is in how to price a job properly.

Free toolMarkup vs margin calculatorEnter cost plus overhead and the margin you want, and see the price before VAT it needs.

VAT

A bathroom refit is work to an existing building, so HMRC’s VAT Notice 708 makes it standard-rated at 20%. VAT Notice 701/7 sets out two exceptions that come up on bathrooms:

  • Zero rate for a disabled person. Providing, extending or adapting a bathroom, washroom or lavatory can be zero-rated where the work is necessary to suit the condition of a disabled person and, where the supply is to that person, the building is their private residence. A bathroom includes a shower or wet room, and the relief extends to the sanitary ware and the immediate decor, retiling included. Get a written declaration of eligibility from the customer, separate from the order or invoice. HMRC says the relief does not cover someone who is elderly but not disabled or chronically sick, or only temporarily disabled.
  • 5% for mobility aids. Grab rails, built-in shower seats or showers containing them, and walk-in baths with sealable doors, supplied and installed in the home of a person aged 60 or over, are reduced-rated, again with a declaration.

NoteOnly the qualifying work is relieved. Retiling the same bathroom years later is standard-rated, and so is a general refit that is not needed for the person’s condition.

What should the exclusions say?

  • Floor joists, boards or subfloor found rotten or damaged, beyond the provisional sum.
  • Asbestos surveys and removal.
  • Moving the soil stack or drainage outside the room, unless drawn.
  • Upgrading the boiler, hot water cylinder or water supply to suit a new shower.
  • Any new circuit or consumer unit work beyond what is specified.
  • Tiles, suite and brassware above the stated allowances, and any items the client supplies.
  • Making good to rooms below or beside, beyond the bathroom itself.
  • Decoration outside the bathroom.

Once a customer accepts a quote, that figure binds you for the work in it, so the exclusions are what protect you when the floor comes up. See is a builder’s quote legally binding?

How does Estimark help with a bathroom refit?

The quote is built from your own price book, with company labour rates, overhead and margin, and the client accepts and signs it online. From the accepted quote, a deposit invoice is raised and a payment plan spreads the balance across stages, each with its own due date and amount. Estimark does not take card payments from your customer.

On Estimark for kitchen and bathroom fitters, the plumber, electrician and tiler sit on one job with their insurance and scheme registration dates. When the floor turns out to be rotten, a variation is raised, priced and signed by the customer at the door or in the portal, and lands on the invoice as its own line. EIC and Minor Works certificates are built in with typed results and a customer signature; notifying the work under Part P stays with the electrician’s scheme or building control.

Sources

Questions

Frequently asked

Does a bathroom refit need Building Regulations approval?

Replacing a bath, toilet, basin or sink does not. Installing a bathroom that involves new plumbing may, and notifiable electrical work needs a registered electrician or a building control notice. Check with building control if the layout or drainage changes.

Is electrical work in a bathroom notifiable?

In England, a new circuit, such as one for an electric shower, is always notifiable, and so is any addition or alteration to existing circuits in the space around the bath or shower. Replacing a fan on its existing cabling is not.

What extractor fan rate does a bathroom need?

Approved Document F sets a minimum of 15 litres per second for an intermittent bathroom fan, or 8 litres per second at the high rate for a continuous system, extracting to the outside.

Is VAT charged on a bathroom refit?

Yes, at 20% where the builder is VAT-registered. Work necessary to suit a disabled person’s condition in their own home can be zero-rated with a declaration, and some mobility aids for people aged 60 or over are charged at 5%.

Do I need to tell the water company about a new bath?

Only for a bath holding more than 230 litres to the centre line of the overflow, in England and Wales. Give notice and wait for consent; if the company does not respond within ten working days, consent is deemed.

Who pays if the floor is rotten under the old bath?

Whoever the quote says. If you included a provisional sum or an exclusion for hidden defects, the extra is a variation the client pays. If the quote was a fixed price with no such wording, the risk may sit with you.