Job costing

How to track job profit while the job is still running

6 min read

The short answer

To track a job’s profit while it runs, keep five numbers up to date each week: the budget, broken into labour, materials, plant and subcontractors from the priced quote; the cost committed so far, counting orders when they are placed rather than when the invoice arrives; the cost actually incurred, with labour at its true cost rate from timesheets; the value earned to date, from what you have applied for or a fair measure of progress, plus agreed variations; and a forecast of the cost to finish. Value earned minus cost to date is the margin so far. Contract value minus forecast final cost is where the job will end. If the forecast margin falls below the margin you priced, find out which cost head moved while there is still time to act.

At a glance

Budget from
The accepted quote, by cost head
Book costs when
Committed, not when invoiced
Labour at
Hours × true cost rate
Margin to date
Value earned − cost to date
Forecast margin
Contract value − forecast final cost
How often
Weekly; a formal CVR monthly

Why do jobs that looked profitable lose money?

Usually because the cost was known before anyone looked at it. The hours were on timesheets, the materials were on orders, the subcontractor’s price was agreed, but nobody added them up against the budget until the final invoices came in. By then the only thing left to do with the answer is learn from it.

The other common cause is value that was never claimed: extra work done on a nod, with no variation priced and agreed. The cost lands in full and the value never does. How to stop that is in variations in construction.

How do you set the budget for a job?

From the quote the customer accepted, split into the same heads you will book costs to: labour, materials, plant, subcontractors and preliminaries. If the quote was priced as one lump, split it now while you still remember how you got to the number. A budget that cannot be compared head by head can only tell you that something is wrong, not what.

Keep the original budget fixed and add approved variations to it separately, so you can always see what you priced and what was added.

Which costs should you count, and when?

Cost headCount it whenFrom
LabourThe hours are workedTimesheets booked to the job, at the true cost rate including employer’s costs
MaterialsThe order is placedPurchase orders, then deliveries and supplier invoices
PlantThe hire startsHire orders and off-hire dates
SubcontractorsThe work is doneTheir applications or your own measure of what they have done
PreliminariesThe week passesWeekly cost of site set-up, welfare, skips and supervision

Counting materials when the order is placed is the habit that matters most. A supplier invoice can arrive six weeks after the delivery; the order tells you today what the job has spent. The same goes for labour: a timesheet on a Friday is a cost that week, whatever day payroll runs.

How do you measure the value earned so far?

On a job with applications for payment, the value earned is what you have applied for, less anything you know will not be certified. On a domestic job with stage payments, it is the stages reached plus a fair estimate of progress on the current stage, not the payments received. Add variations that have been agreed, and leave out ones that have not.

Be strict about value and generous about cost. A margin that looks healthy because the value is optimistic is worse than no number at all.

How do you forecast where the job will finish?

For each cost head, estimate what is left to spend, and add it to the cost so far. Do it from the programme, not from the remaining budget: if the groundworks are three weeks behind, the labour to finish is not what is left in the labour budget. An illustrative weekly check on a £120,000 extension:

HeadBudgetCost to dateForecast to finishForecast final
Labour£38,000£24,500£17,000£41,500
Materials£34,000£21,000£12,500£33,500
Plant£6,000£3,800£2,000£5,800
Subcontractors£22,000£9,000£13,000£22,000
Total£100,000£58,300£44,500£102,800

Illustrative figures for a worked example. Contract value £120,000 including £2,500 of agreed variations.

The job was priced at a £17,500 margin on £117,500. With the variation it is now worth £120,000, and the forecast final cost is £102,800, so the forecast margin is £17,200, about 14.3% against the 14.9% priced. Labour is the head that moved, and it moved because the job is running long. That is a question for the programme this week, not for the final account in four months.

Free toolMarkup vs margin calculatorTurn a forecast margin into a percentage both ways, and check what price a job needed to reach the margin you wanted.

What are the warning signs?

  • Labour cost to date running ahead of progress, week after week.
  • Materials ordered beyond the budget quantity with no variation behind them.
  • Hours booked to the job with no rate, so they cost nothing on paper.
  • Variations done but not priced, or priced but not agreed.
  • Value earned to date higher than the work a visitor to site would recognise.
  • A forecast that has not changed for a month on a job that has.

Once a month, put the same figures through a full cost value reconciliation, with accruals, prepayments and the adjustments a weekly check skips. The method is in what is cost value reconciliation.

How does Estimark track job profit?

When a quote is accepted, Estimark copies its lines to the job, and they become the job’s budget unless you take a baseline. Costs land on the job as the work happens: hours booked from the iPhone or Android app are costed at the rate entered or the person’s, trade’s or subcontractor’s cost rate, and hours with no rate are flagged rather than counted as free. Purchase orders show as committed cost, goods received against them count before the invoice arrives, and supplier invoices are matched to the order and the delivery before they are approved, which the site team can also do from either phone. Approved expenses and supplier invoices count as cost, and approved variations raise the contract value.

On the web, each job shows its budget, committed and actual cost, the forecast final cost, the margin to date and the forecast margin, with a CVR view across jobs and an export to CSV. That is the Job Costing module, included from Core, with orders in purchase orders. See job costing and CVR.

NoteThe cost and margin screens are on the web, not on the phones. Estimark does not alert you when a job goes over budget; the weekly look at the forecast is still yours to do.

Questions

Frequently asked

How do I know if a construction job is profitable before it finishes?

Compare the value earned to date with the cost to date, counting orders when placed and labour from timesheets, and forecast the cost to finish from the programme. Contract value minus forecast final cost is the margin the job is heading for.

How often should a small builder check job costs?

Weekly for the headline numbers on each live job, and monthly for a full cost value reconciliation with accruals and adjustments.

Should materials count when ordered or when invoiced?

When ordered, as committed cost. The invoice can arrive weeks later, and by then the money has already been spent as far as the job is concerned.

What labour rate should I use for job costing?

The true cost of an hour, including employer’s National Insurance, pension, holiday and non-productive time, not the hourly pay rate and not the rate you charge.

Is job costing the same as a CVR?

No. Job costing records what each job costs as it happens. A cost value reconciliation compares that cost with the value earned, with adjustments, usually monthly, to report the margin properly.