Running the business
How to win public sector construction work as a small contractor
The short answer
Since 24 February 2025, new public procurements in England, Wales and Northern Ireland run under the Procurement Act 2023, and their notices go on Find a Tender, the central digital platform. That includes advertised opportunities below the main thresholds: from £12,000 including VAT for central government buyers and £30,000 for councils and other bodies. Devolved Scottish bodies follow their own legislation. Most small construction contracts sit below the works threshold of £5,193,000 including VAT, where the buyer cannot run a separate pre-qualification stage unless the works are worth at least £135,018 or £207,720. To win the work, register on Find a Tender and keep your core supplier information current, save searches for your trades and region, read the award criteria before deciding to bid, and back every claim with evidence. Public buyers must pay valid invoices within 30 days, and so must contractors paying subcontractors on public work.
At a glance
- Law for new procurements
- Procurement Act 2023, from 24 February 2025
- Where notices go
- Find a Tender, the central digital platform
- Works threshold, 2026 and 2027
- £5,193,000 including VAT
- Below-threshold notice, central government
- From £12,000 including VAT
- Below-threshold notice, other buyers
- From £30,000 including VAT
- Paying you
- 30 days from a valid invoice, s.68
- Paying your subcontractors
- 30 days, implied by s.73
- Framework term
- Up to 4 years, s.47
What changed under the Procurement Act 2023?
The Act replaced the Public Contracts Regulations 2015 for procurements started on or after 24 February 2025. A procurement started before then, or a framework set up under the old rules, carries on under the old rules until it ends, so for a while you will see both.
- One platform. Notices for new procurements go on Find a Tender, which the Act calls the central digital platform, above and below the thresholds.
- One supplier record. You register once and hold your core supplier information there, instead of retyping the same details for every buyer.
- Below-threshold rules in the Act itself. Lower-value contracts get their own notice, payment and pre-qualification rules in Part 6.
- New tools for buyers. Dynamic markets replace dynamic purchasing systems, and open frameworks are new.
- Payment terms written in. Thirty days from a valid invoice is implied into public contracts and into every sub-contract under them.
NoteScotland is outside most of this. Devolved Scottish authorities are excluded from the Act and continue under Scottish procurement legislation. Welsh and Northern Ireland bodies are covered by the Act, with some differences of their own.
Where are public sector construction tenders published, and how do you find them?
On Find a Tender. Since 24 February 2025 both above and below-threshold notices for new UK procurements are published there, except below-threshold notices in Scotland. Below-threshold opportunities used to sit on Contracts Finder; under the Act a buyer must put a below-threshold tender notice on the central digital platform before advertising it anywhere else. Contracts Finder still carries notices for procurements started under the old regulations, and Public Contracts Scotland carries Scottish below-threshold work.
Tender notices classify what is being bought by CPV code, the standard procurement vocabulary, and give a geographical classification where one can be described. Search by the codes for your trades and the regions you work in, save the search, and switch on email notifications. Find a Tender needs a GOV.UK One Login for both.
The notices worth watching
- Pipeline notice. A buyer expecting to spend more than £100 million in the coming year publishes one within 56 days of the year starting, listing contracts over £2 million it plans to tender in the next 18 months.
- Planned procurement notice and preliminary market engagement notice. Early warning that a tender is coming, sometimes with an invitation to talk to the buyer first.
- Tender notice or below-threshold tender notice. The opportunity itself, with the deadline.
- Contract award notice and contract details notice. Who the contract went to. Useful for knowing your local market and the firms you are up against.
NoteNot everything is advertised. A buyer that asks for quotes only from pre-selected suppliers, such as firms on a framework, does not have to publish a below-threshold tender notice, and call-offs under a framework have no tender notice at all. You see that work, if at all, as a contract details notice after the award. Getting onto those lists is a job in its own right.
Free toolPublic tenders by trade and regionA free email every Monday with the construction notices published in the last seven days for the trades and regions you choose.What are the thresholds in 2026 and 2027?
Thresholds decide which rules apply. Values are estimated including VAT, and the figures below apply to procurements started from 1 January 2026; GOV.UK gives them for 1 January 2026 to 31 December 2027.
| Contract | Threshold including VAT | What it means |
|---|---|---|
| Works contract | £5,193,000 | At or above: the full regime for a public contract |
| Goods or services, central government buyer | £135,018 | At or above: the full regime |
| Goods or services, other buyers such as councils | £207,720 | At or above: the full regime |
| Below-threshold works, central government | £135,018 | From here the buyer may add a separate suitability stage |
| Below-threshold works, other buyers | £207,720 | From here the buyer may add a separate suitability stage |
| Notifiable below-threshold contract, central government | £12,000 | If advertised, a below-threshold tender notice first |
| Notifiable below-threshold contract, other buyers | £30,000 | If advertised, a below-threshold tender notice first |
Procurement Act 2023, Schedule 1 and sections 85 and 87, as amended from 1 January 2026 (PPN 023).
For a small contractor the below-threshold rules matter most, because nearly every job you would bid for sits under the works threshold. Under section 85 a buyer inviting tenders for a below-threshold contract cannot screen bidders out on financial standing, legal status or technical ability before assessing the tenders, except for works contracts at or above £135,018 for central government or £207,720 for other buyers. Under section 86 it must consider the barriers small firms face before it invites tenders.
Below-threshold competitions can also be reserved. Central government bodies can reserve them to UK suppliers or to a single county or London borough under PPN 005, and since the Local Government (Exclusion of Non-commercial Considerations) (England) Order 2026 came into force, councils in England can reserve them to suppliers based in their local area or the UK. Buyers can also reserve below-threshold competitions to small businesses and voluntary, community and social enterprises.
How do you register on the central digital platform?
- 01Create a GOV.UK One Login and sign in to Find a Tender.
- 02Register your organisation as a supplier. You get a unique identifier, or can use one you already hold, such as your Companies House number.
- 03Complete your core supplier information. Four categories: basic details such as name, address, VAT number, legal form and whether you are an SME; economic and financial standing from your latest accounts; connected persons, such as people with significant control over the business; and any exclusion grounds, such as relevant convictions.
- 04Share it with the buyer when a procurement asks you to, before the end of the tendering period. Only buyers you share it with can see it.
- 05Keep it current. Check it before every bid, especially after a change of directors or new accounts.
A buyer cannot award you a notifiable below-threshold contract until you are registered on the central digital platform, have submitted the information the regulations specify and have given it your unique identifier. Register before you need to.
What are frameworks and dynamic markets?
A framework is a contract between a buyer and one or more suppliers setting the terms on which future contracts, called call-offs, will be awarded. It is awarded once, after a competition, and most last no more than four years. Call-offs are then awarded to the firms on it, either directly or through a competitive selection process among them, and no tender notice is published for a call-off. A firm that is not on the framework does not see the work.
An open framework is new under the Act. It must be re-opened to new suppliers at least once in its first three years and at least every five years after that, for up to eight years in all, so missing the first round no longer locks you out for the whole term.
A dynamic market is a list of qualified suppliers that must stay open to new members at any time. You apply, show you meet the conditions for membership, and are then eligible for the contracts awarded through it. Dynamic markets replace the old dynamic purchasing systems and can be used for works as well as goods and services.
Watch for the tender notice that sets up a framework or a dynamic market in your trade and region. It is the entry point for contracts that will not be advertised individually.
What does a small contractor’s bid need?
What the notice and the tender documents ask for, evidenced. Section 22 limits what a buyer can demand as a condition of participation, and the limits work in a small firm’s favour:
- Conditions must be a proportionate way of checking your legal and financial capacity or technical ability, judged against the nature, complexity and cost of the contract.
- A buyer cannot demand audited accounts unless the Companies Act already requires yours to be audited.
- It cannot require contract insurance to be in place before award. It can ask you to show you will have it from the start, and employers’ liability insurance can be required because the law already requires it.
- It cannot require a particular qualification without accepting equivalents, or require a previous contract with a particular authority.
- You can rely on another supplier to meet a condition if you bid jointly, or if the buyer is satisfied you will enter into legally binding arrangements for it to carry out part of the work or guarantee it.
Beyond the conditions, tenders are assessed against published award criteria, usually a mix of price and quality. Quality questions can ask for a method statement, a programme and your health and safety arrangements, and conditions of participation for technical ability can ask for evidence of similar work. Hold accreditations because a buyer you want to work for asks for them or an equivalent, not on spec. Industry pre-qualification questionnaires for works can still be used where they meet the Act.
Above-threshold central government tenders also score social value, at a minimum of 10% of the total under the current procurement policy note, and other public buyers may choose to apply the same approach. Answer it with specific, measurable commitments; see social value in construction tenders. If your bid relies on subcontractors, have their insurance, competence and CIS details checked before you name them: how to vet a subcontractor before they start.
How do you go from a notice to a submitted bid?
- 01Read the whole notice. Buyer, scope, lots, estimated value, contract length, procedure, conditions of participation, award criteria and weightings, and the deadlines for questions and tenders.
- 02Decide whether to bid. Capacity in the contract period, distance, the cash the job ties up, and whether you can evidence every condition. Log the decision either way.
- 03Check your Find a Tender registration and update your core supplier information.
- 04Get the tender documents from the route the notice gives for submitting tenders, and diary the clarification deadline.
- 05Ask questions in writing early. A vague specification or an unclear pricing schedule is cheaper to clarify than to price around.
- 06Assemble the evidence for each condition: case studies, references, accounts, an insurance letter confirming cover from the start, health and safety documents, and any accreditation asked for or its equivalent.
- 07Price it from your own rates. Preliminaries, subcontract quotes, any social value commitments, and the payment terms. Compare your total with the buyer’s estimated value and understand any big gap.
- 08Write the quality answers to the criteria. Answer the question asked, within the word count, with evidence from real jobs.
- 09Line up your subcontractors and confirm prices, availability and the arrangements you are relying on.
- 10Submit early, by the stated route, and keep the confirmation.
- 11Read the assessment summary. On an above-threshold competitive award the buyer must give every bidder whose tender was assessed a summary of its assessment of that tender and of the winning one. In most cases there is then a standstill of at least eight working days before the contract is signed.
How quickly must you be paid, and how quickly must you pay?
Within 30 days of a valid invoice, both ways. Section 68 of the Act implies into every public contract that the buyer pays a sum due within 30 days of receiving the invoice, or of the payment falling due if later. If it considers the invoice invalid or disputes it, it must tell you without undue delay. Section 88 does the same for below-threshold contracts.
Section 73 implies the same 30-day term into every public sub-contract, meaning any contract substantially for performing part of a public contract. A term that tries to override it has no effect, though the parties can agree to pay sooner.
Central government buyers on contracts over £5 million a year now run payment spot checks down the supply chain under PPN 021, and suppliers who are paid late on public work can complain to the Public Procurement Review Service. On central government contracts of the same size, PPN 018 asks bidders to show they pay at least 95% of invoices within 60 days and all invoices within an average of 45 days. Thirty-day payment helps your cash flow when you are the subcontractor and tests it when you are the main contractor: see cash flow for small builders.
How does Estimark help?
The free public tenders email arrives every Monday with the construction notices published in the last seven days for the trades and regions you pick, each with the buyer, the value, the closing date and a link to the notice. It reads Find a Tender, Contracts Finder, Public Contracts Scotland and Sell2Wales, needs no account, and sends nothing in a week with nothing that fits. It lists notices; it does not bid, and it cannot see framework call-offs or quotes sent only to an approved list.
Inside Estimark, the tender register holds each tender with the client, the site, the value, the return date and the person who owns it, and you record the outcome when you hear, so next year you can see what you bid for and what you won. The estimate is built from your own rates, and the figure the client accepts becomes the job budget.
Sources
- Find a Tender (GOV.UK service)
- Procurement Act 2023, section 22 (legislation.gov.uk)
- Procurement Act 2023, section 68 (legislation.gov.uk)
- Procurement Act 2023, section 73 (legislation.gov.uk)
- Procurement Act 2023, section 87 (legislation.gov.uk)
- PPN 023: 2026 threshold amounts (GOV.UK)
- Guidance: below-threshold contracts (GOV.UK)
- Guidance: central digital platform and publication of information (GOV.UK)
- Guidance: frameworks (GOV.UK)
- Guidance: dynamic markets (GOV.UK)
- Guidance: conditions of participation (GOV.UK)
- PPN 019: requirements to publish on Contracts Finder (GOV.UK)
- Reserving competitions for below-threshold contracts (GOV.UK)
- PPN 021: payment spot checks in public sub-contracts (GOV.UK)
Questions
Frequently asked
Is Contracts Finder still used?
For procurements started under the Public Contracts Regulations 2015 before 24 February 2025, yes, including awards under frameworks set up then. New below-threshold opportunities under the Procurement Act 2023 must be published on Find a Tender first.
What is the works threshold under the Procurement Act 2023?
£5,193,000 including VAT for procurements started from 1 January 2026, set by PPN 023 and the 2025 threshold amendment regulations. Works below that are below-threshold contracts with lighter rules.
Do I need to register on Find a Tender to bid?
For an above-threshold competition the buyer must confirm you have registered and shared your core supplier information through the platform. For a notifiable below-threshold contract you must be registered and give the buyer your unique identifier before it can award to you.
Can a council ask for accreditations as a condition of bidding?
It can ask for qualifications as evidence of technical ability where that is proportionate, but under section 22 it cannot require a particular qualification without accepting equivalents. Below the threshold it cannot run a separate suitability stage at all, except for works from £135,018 or £207,720.
How quickly must a main contractor pay me on public sector work?
Within 30 days of receiving your valid invoice, or of the sum falling due if later. Section 73 of the Procurement Act 2023 implies that term into every public sub-contract, and a term trying to override it has no effect.
Does the Procurement Act apply in Scotland?
Not to devolved Scottish authorities, which continue under Scottish procurement legislation. Scottish below-threshold notices are not published on Find a Tender; Public Contracts Scotland carries Scottish opportunities.
Read next
How to vet a subcontractor before they start
Insurance, CIS verification, cards and competence, employment status, and what to keep on file.
Cash flow for small builders
Why profitable jobs still run out of cash, a weekly forecast, and the payment terms that change it.
Estimark: tenders and estimating
A tender register, a price book of your own items and rates, and the accepted figure kept as the job budget.
Public construction tenders by trade and region
A free weekly email of construction notices for the trades and regions you choose.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee and no card needed.