Getting paid

How to make an application for payment, and chase it

7 min read

The short answer

Find the payment terms in the contract first: the application dates, the due date, the final date for payment and what an application must contain. Value everything done to date, cumulatively, including approved variations and any materials the contract lets you claim, take off retention and the amount certified before, and send it in writing on the application date, stating the sum and how it was calculated. Diary four dates: the due date, the last day for the payer’s payment notice, the last day for a pay less notice, and the final date for payment. If no payment notice arrives you can give your own notice, and if no valid pay less notice arrives the notified sum is payable in full. If the final date passes unpaid, you can give seven days’ notice to suspend work, claim statutory interest, or refer the dispute to adjudication. None of this applies to a contract with a homeowner for work on their own home.

At a glance

Valuation
Cumulative, less retention and previous payments
Scheme due date
Later of 7 days after the period or the claim
Scheme final date
17 days after the due date
Payer’s payment notice
Within 5 days of the due date
Scheme pay less notice
At least 7 days before the final date
Suspension
At least 7 days’ notice, with the grounds
Homeowner’s own home
Not covered (s.106)

What do you need from the contract before you apply?

  • How often you apply, and on what date: monthly on the last working day is common, but the contract decides.
  • What the application must contain and who it goes to, by name and by method.
  • How the due date and the final date for payment are worked out.
  • Who gives the payment notice, and the period for a pay less notice.
  • The retention percentage, any cap, and when each half is released.
  • Whether materials on site or off site can be included, and on what evidence.

Where the contract does not set these, the Scheme for Construction Contracts fills the gaps. In England and Wales, on the Scheme, the relevant period is 28 days, a payment falls due on the later of 7 days after the end of the period or the making of your claim, and the final date for payment is 17 days after the due date.

NoteSection 106 of the Construction Act excludes a contract with a residential occupier: work principally on a house or flat the customer lives in or intends to live in. With a homeowner, the payment terms are whatever your quote and contract say.

How do you value the work?

Cumulatively. Each application states the gross value of everything done since the start, not just this month, and then takes off what has already been certified. That way an item under-valued last month is caught up this month without a separate argument.

LineApplication 3
Contract works complete to date£84,000
Approved variations to date£6,500
Materials on site (where the contract allows)£3,500
Gross valuation to date£94,000
Less retention at 5%−£4,700
Net valuation to date£89,300
Less previously certified−£61,750
Amount applied for this period, excluding VAT£27,550

Illustrative figures for a worked example.

Back each line with something the payer can check: a measure against the schedule or the bill, the signed variation instruction, the delivery note for materials. Dayworks go in with their signed sheets; see dayworks in construction. Retention, and how to get it back, is in what is retention.

Free toolPayment application templateA free application with the cumulative valuation, the deductions in the right order and the dates that start the payment clock.

How and when should you send it?

On the date the contract says, by the method it says, to the person it names. State the sum you consider due and the basis on which it is calculated: under the Scheme a written notice of the amount and its basis is a claim, and that is the same information a payment notice has to carry. Keep proof of when it was sent and received, because every later date runs from it.

Send an application, not an invoice, where the contract runs on applications. A VAT invoice issued before you are paid creates a tax point; an application does not. Why the two documents are not interchangeable is in applications for payment vs invoices.

Which dates should you diary?

  1. 01The due date, set by the contract or, on the Scheme, the later of 7 days after the period or your claim.
  2. 02The payment notice deadline: the payer, or the person the contract names, must give a payment notice no later than 5 days after the due date.
  3. 03The pay less deadline: the contract’s period before the final date or, on the Scheme, no later than 7 days before it.
  4. 04The final date for payment: the contract’s date or, on the Scheme, 17 days after the due date.
Free toolPayment date calculatorPut in the application date and the contract’s periods, and get the due date, both notice deadlines and the final date.

What can you do when the dates pass?

No payment notice

If the payer’s notice does not arrive in time, section 110B lets you give your own notice of the sum due and its basis at any time after the deadline, and the final date moves back by the number of days you were late in giving it. Where the contract lets your application stand as that notice, and you sent it before the payer’s deadline, it already counts as one.

No valid pay less notice

The notified sum is payable in full on the final date. A pay less notice that is late, or does not state the sum and how it was worked out, does not reduce it. The detail is in what is a pay less notice.

Not paid by the final date

  • Chase it in writing the next day, naming the sum, the application and the final date that has passed.
  • Suspend. Section 112 lets you suspend any or all of your work after giving at least seven days’ notice of your intention, stating the grounds.
  • Claim interest and compensation on a late commercial payment; see getting paid faster.
  • Adjudicate. Either party can refer a dispute to adjudication at any time, and a decision comes in weeks; see how construction adjudication works.

How does Estimark handle applications for payment?

In Estimark’s payment applications module, included from Pro, an application belongs to the job and carries its gross valuation to date, the retention percentage and amount, the total certified before, worked out from the earlier certified applications, and the net sum. When it is certified, Estimark raises the invoice with the right VAT, reverse charge included, and sends it to your accounting software; if it then goes unpaid, the invoice is chased automatically 3, 7, 14 and 30 days after it falls overdue. A pay less notice against it is recorded with its amount and reason, and retention held and due for release is tracked per job. See payment applications and retention.

Each application carries a due date, a final date for payment and the payment notice and pay less deadlines worked from them, and the iPhone and Android apps count each one down on the application.

NoteEstimark sets the due date 30 days after the application date and the final date 14 days after that. If your contract or the Scheme gives different periods, use the contract’s dates and the payment date calculator above.

Sources

Questions

Frequently asked

What should an application for payment include?

The gross value of work done to date, approved variations, any materials the contract lets you claim, retention deducted, the amount certified before, and the sum applied for, with the basis of each figure and the dates the contract asks for.

When is an application for payment due?

When the contract says. If it is silent, the Scheme for Construction Contracts makes a payment due on the later of 7 days after the end of the period, which is 28 days if the contract sets none, or the making of your claim.

What happens if the client does not respond to my application?

If no payment notice is given you can give your own notice under section 110B, or your application may already be the notified sum under the contract. Without a valid pay less notice, the notified sum is payable in full on the final date.

Can I stop work if an application is not paid?

Yes, if the sum is not paid by the final date. Section 112 of the Construction Act lets you suspend after giving at least seven days’ notice of your intention, stating the grounds.

Do applications for payment apply to work for homeowners?

Not under the Construction Act. Section 106 excludes contracts with a residential occupier for work on the home they live in or intend to live in, so the payment terms come from your own quote and contract.

Read next

Run the paperwork once.

Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee and no card needed.

Build on a solid foundation.

Run the whole business without an implementation project and without legacy baggage. Every plan starts with 14 days free. No card needed.

Estimating · Jobs · Invoicing · CIS · H&S · Reactive maintenance