Handover
Snagging and handover: a checklist for small builders
The short answer
Finish a job in four steps. Walk it yourself first and snag it room by room, with a photo, a location and a named trade for each item. Put those right and sign each one off before the customer sees the work. Then walk it with the customer, agree any items they add in writing, and set a date for each. Hand over a pack with the certificates the work needs, such as the competent person scheme certificate for notifiable electrical or gas work, the building control completion certificate where building control was involved, guarantees and manuals, and on a project with more than one contractor the CDM health and safety file. Finish by telling the customer, in writing, how to report a defect after handover.
At a glance
- First snag walk
- Yours, before the customer’s
- Each snag
- Number, photo, location, trade, due date
- Closed means
- Signed off by a name, with a date
- Competent person certificate
- Within 8 weeks of completion
- Health and safety file
- Projects with more than one contractor
- After handover
- Agree in writing how defects are reported
What order should the last week of a job run in?
- 01Your own snag walk, a few days before the customer’s, while the trades are still on site.
- 02Put the items right and sign each one off. Rectified by the trade is not the same as checked by you.
- 03Clean. A customer who walks into dust snags the dust.
- 04Collect the paperwork while the people who produced it can still be reached: certificates, test results, guarantees, manuals.
- 05Walk it with the customer. Record what they add, agree a date for each, and say which items are not defects.
- 06Hand over the pack and the keys, and the instructions for reporting anything after.
- 07Invoice the final payment against the agreed completion, not after the last snag closes, unless the contract says otherwise.
Where the contract names practical completion, the walk with the customer usually decides it. What changes legally on that day, and who decides it, is in what is practical completion.
How do you run a snag walk that does not come back?
Go room by room in the same order every time, top to bottom and left to right, and give every item five things: a number, a photo, a location precise enough to find it again, the trade responsible, and a due date. "Paint touch-up, landing" sends a decorator hunting. "Item 14, first-floor landing, scuff on skirting left of bathroom door, photo" does not.
- Doors and windows: open, close and lock every one, check seals and handles.
- Every tap, every waste, every radiator, every socket and switch.
- Finishes in raking light: walls, ceilings, sealant lines, grout.
- Floors: level, gaps at thresholds, protection lifted and damage under it.
- Outside: drainage, pointing, making good where scaffold ties were, the skip area.
What separates a snag from a defect, and why a list kept on paper causes arguments later, is in what is a snagging list.
Which certificates should the customer get?
It depends on the work, and the customer will need them when they sell. A solicitor’s searches will look for them.
| Work | What the customer should get |
|---|---|
| Notifiable work done under a competent person scheme, such as a new consumer unit or a boiler | The scheme’s certificate of compliance. GOV.UK says the installer gives it within 8 weeks of completion and tells the council where needed. |
| Electrical work | The installation or minor works certificate the electrician issues, as well as any scheme certificate. Which work is notifiable is in Part P. |
| Work approved through building control, such as an extension or a structural alteration | The local authority’s completion certificate or, where a registered building control approver was used, a copy of the final certificate it gave the council. See building control completion certificates. |
| A project with more than one contractor | The CDM health and safety file. |
| Products with their own guarantees | The guarantee documents, registered in the customer’s name where the manufacturer asks for that. |
The health and safety file comes from CDM 2015. Where there is more than one contractor, regulation 5(1) requires a principal designer, who prepares the file during the project, and regulation 12(10) requires it to be passed to the client at the end. Where there is no principal designer by then, the principal contractor passes it on. It holds what somebody would need to know to work on the building safely later: where the services run, what is in the walls, which materials need care.
What else goes in the handover pack?
- A one-page summary: what was done, the dates, and who to call.
- The certificates above.
- Manuals for every appliance and system installed, and how to service them.
- Where the stopcock, the isolation valves and the consumer unit are, with a photo of each.
- Paint colours, tile and flooring references, so a repair matches.
- The agreed list of any outstanding items, with dates.
- How to report a defect after handover, and what counts as one.
Collect each document when it is issued, not in the last week. The electrician who tested in week three is easier to reach in week three.
What happens to defects after handover?
With a homeowner, section 49 of the Consumer Rights Act 2015 requires the work to be done with reasonable care and skill whatever the contract says, so a fault in your work is yours to put right after handover as well as before. A defects liability or rectification period only exists if the contract creates one. If it does, it says how long, how defects are notified and whether retention is held until the end of it, which is all in the defects liability period.
Either way, write down how the customer reports a problem, and keep the photos from your snag walk. A photo of a finished, clean skirting dated on handover day settles most arguments about who caused a dent three weeks later.
How does Estimark handle snagging and handover?
Snags are raised against the job on the iPhone or the Android app, with or without signal, with a photo, a location down to the floor and the room, a trade, an assignee and a due date, and run through open, in progress, rectified and signed off, with the name and date of whoever signed them off. You can also send the customer a link where they add their own snags with photos, without an account, and each one lands on the same list. That is the Defect Management module, included from Core.
A handover pack is built against the job from the documents already on it, compiled into one PDF or a zip where files are attached, and emailed to the customer. Electrical and gas certificates, from the EIC and minor works certificate to the CP12, are produced on the job and print as PDFs. After handover, warranty periods are tracked per job and the customer can report a warranty defect through their portal: see warranty management and the handover and defects tour.
NoteEstimark keeps the certificates and the pack; it does not notify building control or a competent person scheme for you. That is still done through the scheme or the building control body.
Sources
Questions
Frequently asked
Should the builder or the customer do the snagging?
Both, in that order. Walk the job yourself first and close your own list, then walk it with the customer and record what they add. A customer who finds ten items on a job you had already snagged has less reason to doubt the rest.
How long does a customer wait for a competent person scheme certificate?
GOV.UK says the installer gives the certificate within 8 weeks of completion. It serves as evidence the work complies with building regulations, and it shows up in a solicitor’s searches when the house is sold.
Do I have to give a homeowner a health and safety file?
Where the project had more than one contractor, yes. CDM 2015 requires a principal designer to prepare the file and pass it to the client at the end, or the principal contractor where there is no principal designer by then. A one-contractor job has no file requirement.
Can I hold the final invoice until the snags are cleared?
The contract decides when the final payment is due. If it ties payment to completion, invoice on completion and list any outstanding items with dates, so a short list does not hold up the whole sum.
Is a snag the same as a defect?
Not quite. A snag is an item found before or at handover, usually minor and visible. A defect is a fault found later, often after the customer has moved in. The same records cover both: what it is, where it is, who put it right and who signed it off.
Read next
How to keep a site diary that holds up in a dispute
What to record each day, who should write it, and why a diary written on the day beats memory.
Building control completion certificates
Which route, the notices, the inspections and the certificate a homeowner will ask for when they sell.
What is a snagging list, and what makes one hold up?
What each item needs, snags against defects, and what happens to the list after handover.
Snagging list template
Numbered items with a location, a trade and the sign-off that makes retention release due.
Estimark: defect management
Numbered snags with a photo, location, trade and assignee, tracked to a named sign-off.
Estimark pricing
Every plan, what it includes, and the 14-day free trial.
Snagging app
Snags logged on site with photos, assigned to a trade and signed off before handover.
Retention release request template
Ask for retention back at practical completion and at the end of the defects period.
Run the paperwork once.
Estimating, jobs, invoicing, CIS and compliance in one place. 14 days, full access, no implementation fee and no card needed.